Economic Regeneration Strategy Action Plan - Review and Update
AgreedCommittee3 papers
Economic Regeneration Advisory Board agreed this item on Wednesday 22 February 2017. Below is the council's own wording, with the papers it was decided on.
Decision Notice D170017MEM The report provided a detailed overview of the progress made in delivering the Economic Regeneration Strategy Action Plan during 2016. Overall, good progress was being made on a wide range of initiatives and these were set out in Annex 1 to the report. It was indicated that ‘business advice and support’ would also offer guidance regarding the changes to business rates and the Borough Council would continue to lobby Government on behalf of local businesses. Business rates represented a significant impact to many businesses and this approach was supported. In addition, it was confirmed that the business support workshops would be held in Kings Hill on 28 February 2017. Reference was made to the three year survival rates, set out in Annex 2 to the report, and it was suggested that comparisons throughout Kent and the United Kingdom be included in future to provide context. The award of £4.64m of Local Growth Fund Round 3 funding towards the Leigh Flood Storage Area, including Hildenborough, and East Peckham was reported and welcomed by Members. RECOMMENDED: That (1) the Borough Council Economic Regeneration Strategy Action Plan update, as set out in Annex 1 to the report, be endorsed; (2) the amendments to the targets relating to certain indicators reflecting ‘previous performance’, as set out in paragraph 1.2.7 of the report, be agreed; and (3) the priorities for 2017/18, as set out in paragraph 1.3.1 of the report, be agreed.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
1.1.1 At the Economic Regeneration Advisory Board on 23 June 2015, Report ERG 15/13 presented the Borough Economic Regeneration Strategy and Action Plan. It was recommended that the Borough Economic Regeneration Strategy be approved subject to a minor amendment to the ‘success measure’ for securing high speed broadband services across the Borough to reflect the Government’s ambition of 95% by 2017.
1.1.2 This report provides the Board with information on progress regarding the actions set out under Chapter 8 of the Borough Economic Regeneration Strategy, covering the following topics:
• Business Advice and Support • LEADER Programme • Loan Funding to Local Businesses • Better Business for All • Skills Development • Broadband • Work Readiness • Inward Investment • Infrastructure Projects • Tourism • Town and Retail Centres • Tonbridge & Malling Local Plan
1.2Progress to Date
1.2.1 Progress on delivering the Action Plan is set out in Appendix 1. This illustrates that overall good progress is being made on a wide range of initiatives.
1.2.2 By using a RAG analysis of the actions set out in the Strategy, one can see that there are no longer any projects that have a ‘red’ status. The new Kent and Medway Business Fund officially launched on 12 January 2017 and will be allocating £5 million of 0% interest loans to Kent businesses during 2017.
EconRegenAB-NKD-Part 1 Public 22 February 2017 2
1.2.3 There have also been a number of achievements over this period, most notably the award of £4.64m of Local Growth Fund Round 3 funding towards the Leigh Flood Storage Area (including Hildenborough) and East Peckham, as well as a well-used programme of business support.
1.2.4 Unlike the update for 2015, there is now enough statistical information to start illustrating initial trends, as set out in Appendix 2. Under the heading ‘Previous Performance’, some of the figures are set out in bold. These are figures that have either recently become available or are modifications of previous estimates. This has meant that some of the figures for 2013 and 2014 are quite different to those originally set out. For example, the 3 year business survival rate for 2013 was originally estimated at over 70%, and this has subsequently been downgraded to 60.2%.
1.2.5 As is evident from the information in Appendix 2, most of the trends are moving in a positive direction. However, the number of VAT de-registrations was higher than expected for 2015 (540). Despite this, there was still a net gain of businesses of 235 (775 VAT registrations minus 540 VAT de-registrations).
1.2.6 In addition, the 3-year survival rate information is still awaited for 2015. However, it is highly unlikely that the target of 80% survival will be met, given that the original benchmark statistics referred to in 1.2.3 have been downgraded.
1.2.7 It is therefore, proposed that the targets relating to certain indicators are amended to reflect this in the following way:
Follow Economic Regeneration Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.