That (1) the recent award of £20,231 from the Government’s Local Authorities Parks Improvement Fund be used to progress urgent reinstatement works to the Tonbridge Castle Motte with any balance funded from the General Revenue Reserve; and (2) a supplementary estimate of £20,000 be approved, funded from the General Revenue Reserve, to progress high priority repair works to Council owned bridges identified in the external Structural Engineer’s inspection report.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
This report sets out for Council two unbudgeted projects which need to be progressed without delay. The projects relate to the reinstatement of the path and fencing on the Tonbridge Castle Motte and high priority health & safety repairs to a number of bridges owned by the Council.
1.1Financial Procedure Rules
1.1.1 Members of Council will be fully aware that each year Full Council is responsible for setting the budget, including the allocation of resources to different services and projects.
1.1.2 Any proposal to incur unbudgeted expenditure after Full Council has approved the budget or Capital Plan must be submitted to the Executive for approval. In exceptional circumstances supplementary estimates for revenue and capital expenditure can be reported directly to Full Council for approval.
1.2Tonbridge Castle Motte
1.2.1 Due to high winds over the weekend of 16th/17th March a large oak tree located on the Motte at Tonbridge Castle fell, causing substantial damage to the paths and fencing. A picture of the damage caused by the tree is shown in the photograph at Annex 1. A specialist contractor was employed to remove the fallen tree together with another adjacent tree assessed by the contractor to pose a health & safety risk to the public. The cost of the works to remove the two trees, has been met from the 2018/19 health & safety of trees revenue budget.
1.2.2 The damage is both unsightly and also prevents the public accessing the Motte. The pathway on the Motte is extremely popular and also forms part of the Tonbridge Castle audio tour. Quotations to reinstate the path and the fence are currently being sought and liaison is being undertaken with English Heritage to enable the works to be progressed without delay. The Castle is a high profile tourist attraction in the borough with the Motte a backdrop for a wide range of events on the Castle lawn and for wedding parties.
Council - Part 1 Public 09 April 2019 2
1.2.3 An initial budget estimate of £20,000 has been identified and more accurate costings will be available for Council to consider at the meeting.
1.2.4 With regard to funding of the works Council’s attention is drawn to a recent award to the Council of £20,231, from the Government’s Local Authorities Parks Improvement Fund. A copy of the award letter is attached at Annex 2. Council will note in the letter “ the expectation the award will be used to undertake remedial and renovation works to existing parks” The criteria does allow for addressing health and safety concerns and references repairs to essential footpaths and installation of the barriers. It is therefore felt appropriate to allocate this government funding to the works required to the Motte, with any balance funded from the General Revenue Reserve.
1.3Repairs to Bridges
1.3.1 The Council owns and is responsible for the upkeep of 28 bridges across the borough. The majority of the bridges are located in the Council’s Country Parks and on larger areas of public open space including the Racecourse Sportsground in Tonbridge.
1.3.2 Following a review of the bridge inspection regime earlier this year, in accordance with the Departmental Risk Register, a new programme of inspections has been agreed and implemented. Under the new regime, all bridges will be visually inspected by Officers from Technical Services on a quarterly basis, with a structural inspection undertaken every 2 years by an external Structural Engineer.
1.3.3 An external Structural Engineer has recently completed an inspection of all the bridges and a report has been received. The report identified high, medium and low priority works. High priority works are defined as essential works to be undertaken within the next 3-12 months, medium priority works to be progressed within the next 2 years, and finally low priority works to be monitored in future inspections.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.