Waste Services Contract

Agreed Committee 2 papers

Street Scene and Environment Services Advisory Board agreed this item on Wednesday 30 October 2019. Below is the council's own wording, with the papers it was decided on.

ItemSSE 19/24

Resolved

Decision Notice D190077MEM The report of the Director of Street Scene, Leisure and Technical Services provided an update on the new Waste Services Contract which had started on 1 March 2019 and the new and improved recycling services introduced on 30 September 2019. The report also brought forward proposals for the Christmas collection arrangements. In response to a presentation given by Urbaser , Members expressed serious concerns about the contractor’s performance following the implementation of the new household recycling service with particular reference to the food waste collection, the non-completion of rounds and ‘missed’ collections and lack of crew familiarisation with new rounds. Concern was also expressed about the ‘mop-up’ arrangements for undertaking non-completed rounds on the following day and the completion of missed collections; the lack of clarity of the scale of the problem and how it would be resolved and the impact of the current standard of service on residents, Members, the officer team and to the reputation of the Council. In response to a question from a Member, Urbaser agreed to consider a funding contribution towards additional staff costs incurred by the Borough Council. A number of Members reported that the new arrangements for recycling were welcomed by their residents. Particular reference was made to the need to provide clear information on a daily basis to the Borough Council, together with the development of an Action Plan by Urbaser for the resolution of the problems which could be circulated to all Members and reported to the cross-party Waste Contract Member Group. RECOMMENDED: That (1) progress made with the mobilisation of the new service arrangements be noted; (2) the existing Marketing Plan be updated at the end of the calendar year in liaison with the Waste Contract Member Group and an allocation of £40,000 be made in the 2020/21 revenue budget; (3) the proposed Christmas collection arrangements outlined at section 1.7 of the report be noted; (4) an Action Plan to resolve the current issues be developed by Urbaser and circulated to all Members; and (5) a progress report be submitted to the next meeting of the cross-party Waste Contract Member Group.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Street Scene and Environment Services Advisory Board

Summary

This report updates Members on the new Waste Services Contract which started on 1st March 2019, with the new and improved recycling services introduced on 30th September 2019. The report also brings forward proposals for the Christmas collection arrangements.

Background

1.1.1 The Council’s Waste Services Contract was tendered in partnership with Tunbridge Wells Borough Council. Urbaser was appointed as the successful contractor by Cabinet on the advice of this Board, and commenced the delivery of the new contract on 1st March 2019.

In summary:-

 the contract covers the collection of household refuse and the cleansing of streets across the boroughs of Tonbridge & Malling and Tunbridge Wells [in Tonbridge and Malling this involves circa 54,500 households];

 between 1st March – 29th September 2019 the contract matched the service delivery arrangements in the previous contract;

 on the 30th September 2019 the new improved household recycling collection service was introduced, including weekly food waste, plastic bottles, trays, pots and tubs, glass, bottles and jars, paper and card/cardboard, tins and cans, household batteries, small electrical appliances and textiles;

 the new Service includes the change to an opt-in Garden Waste Service for which there is a separate annual charge.

1.1.2 A separate Member Group has been established by this Council to help oversee the implementation of the new contract, and at the June meeting of this

StreetScene&EnvAB-NKD-Part 1 Public 30 October 2019 2

Board Member representation on the Group was agreed. The Group met in August and its next meeting will focus on an assessment of the new Service arrangements, the revised bring bank site arrangements and future marketing and communication to residents.

1.2Contractor Performance

1.2.1 The new Service arrangements were implemented on 30 th September 2019 in accordance with the phased approach previously agreed by this Board.

1.2.2 At the time of writing this report the new Service has just entered its second full cycle of collections, with one cycle taking two full weeks. Liaison is being undertaken on a daily basis with our contractor Urbaser to assess current performance, identify issues and implement actions to resolve them.

1.2.3 The first two weeks of operation have clearly been challenging. Whilst this was to be expected, following the first cycle of collections it is clear that the roll-out has been successful for the vast majority of residents and this has been noted in a number of tweets, emails and feedback from local Members and Parish/Town Councils. It is also clear that given initial informal feedback on tonnages, residents are fully engaging with the new opportunities to recycle their waste kerbside.

1.2.4 It should be noted, however, that for some residents the roll-out has not delivered the services expected, particularly around issues with non-completion of rounds and missed collections. A number of factors have contributed to these issues including crew familiarisation with new rounds, increased waste tonnages and longer than normal tipping times at the disposal sites. In response to these issues Urbaser has deployed additional crews and vehicles to progress non-completed rounds the following day, and ‘mop up’ crews are in place to complete other missed collections. This has also included additional weekend working. The Council has been working with Urbaser to address the root cause of any issue.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Waste Services Contract 19/24Appendix 1 124 KB Download
PDF
Waste Services ContractReport 129 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 42 attended
MD
Councillor Mark DavisChairman, present
MS
Councillor Mrs Sue BellVice-Chair, apologies
GB
Councillor Garry BridgeCommittee Member, present
DC
Councillor David CooperCommittee Member, present
DD
Councillor Dave Davis CEng FICECommittee Member, present
SH
Councillor Steve HammondCommittee Member, present
MH
Councillor Mark HoodCommittee Member, present
FH
Councillor Frani HoskinsCommittee Member, present
AK
Councillor Alan KeeleyCommittee Member, present
DK
Councillor Des KeersCommittee Member, present
AK
Councillor Andrew KennedyCommittee Member, apologies
MM
Councillor Mrs Millie LangridgeCommittee Member, present

All 42 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Waste Services ContractThis decision
  2. South West Kent Waste Services Contract RetenderDecided
  3. Waste Services Contract - Strategic Approach to Service ProvisionDecided
  4. Waste Services UpdateNoted
  5. Waste Services Update ReportDecided
  6. Waste Services ContractNoted

More from Tonbridge and Malling Street Scene and Environment Services Advisory Board

All decisions
MeetingDecisionOutcome
8 Feb 2022 Minutes of Climate Change ForumThat the report be noted. Noted Open
23 Nov 2021 Waste Services UpdateThat the report be noted. Noted Open
31 Aug 2021 Tonbridge Town Centre - Residents Parking Season TicketDecision Notice D210078MEM The report of the Director of Street Scene, Leisure and Technical Services brought forward... Noted Open
31 Aug 2021 Food and Safety Service Plan 2021-24Decision Notice D210079MEM The Council is required to produce a Food and Safety Service Plan by the Food Standards Ag... Noted Open
31 Aug 2021 Updated Air Quality Action PlanDecision Notice D210080MEM The report of the Director of Planning, Housing and Environmental Health provided an updat... Noted Open