Finance, Innovation and Property Advisory Board deferred this item on Wednesday 6 January 2021. Below is the council's own wording, with the papers it was decided on.
Decision Notice D210003MEM The joint report of the Director of Finance and Transformation and the Director of Central Services provided an update on the progress made with the technical implementation and the preparation of content for the new website and advised that, in liaison with the Member Working Group, the launch of the new website had been deferred until June 2021. The delay would mitigate the risk related to local County Council and Police and Crime Commissioner Elections in May 2021 and allow sufficient time for the development of website content and enhanced digital services for local residents. RECOMMENDED : That: (1) the progress in delivering the technical aspects of the website be noted; (2) the deferral of the launch of the website until June 2021 for the reasons set out in the report be endorsed; and (3) the additional costs of the deferral of the launch of the website be built into draft Estimates for 2021/22.
Word for word from the decision Tonbridge and Malling published for this meeting.Source: democracy.tmbc.gov.uk
Report to Finance, Innovation and Property Advisory Board
TONBRIDGE & MALLING BOROUGH COUNCIL
FINANCE, INNOVATION and PROPERTY ADVISORY BOARD
06 January 2021
Joint Report of the Director of Finance and Transformation and Director of Central Services Part 1- Public
Matters for Recommendation to Cabinet - Non-Key Decision (Decision may be taken by the Cabinet Member)
1 PROGRESS WITH NEW COUNCIL WEBSITE
Members are updated on the progress with the technical implementation of the new website, and also on the preparation of the content. In liaison with the Member Working Group, the launch of the website has been deferred until June 2021.
1.1Introduction
1.1.1 Members are aware from previous reports to this Advisory Board that we are currently in the midst of implementing a new Council website.
1.1.2 The outline timetable to deliver the website was reported to the Advisory Board, broken down into:
1) a “technical” component (led by IT Services) and
2) a “content/customer” component led by the Head of Communications and the Head of Customer Services.
1.1.3 This report updates on progress in respect of both components.
1.2Progress with implementation of Technical Platform
1.2.1 The implementation of the website infrastructure has been completed successfully in the Microsoft Azure cloud.
1.2.2 The user administration training has been provided to the relevant staff within Media and communications and IT services. Additional training for the development of the website has been arranged to be delivered.
1.2.3 IT services and Communications team are currently in the process of identifying the existing online and PDF forms for conversion and redevelopment and will be prioritising work based on the go-live deadline.
Finance,Inv&PropertyAB-NKD-Part 1 Public 06 January 2021 2
1.2.4 Content migration is currently in progress and the overall project timeline has been revised to accommodate the efforts involved. The overall project progress is on track.
% Task Name Start Date End Date Complete 61% Overall project progress 26/06/2020 July 2021 *
100% Phase 1: Project Initiation & Planning 26/06/2020 10/07/2020 Phase 2: System Installation & 100% 09/07/2020 28/12/2020 Configuration Phase 3: User Training & Content 50% 29/06/2020 March 2021 * Complete Population In progress Phase 4: Design / Visuals / Brand Delayed 100% 14/07/2020 05/10/2020 Guidelines Not started 25% Phase 5: Template Build 13/11/2020 15/01/2021 Phase 6: Developer Training, Custom 25% 06/10/2020 May 2021 * Developments & Integration 0% Phase 7: UAT 28/01/2021 June 2021 *
0% Phase 8: Go-Live 03/03/2021 July 2021 * August 2021 0% Phase 9: Post Go-Live 09/04/2021 * * Project plan and awaiting confirmation of dates from supplier.
1.1Progress with Website Presentation and Content
1.1.1 Work to review, edit and develop content for the new website is generally progressing well. This work is being led by our Digital Content Editor who was appointed in the summer with approximately one-third of the main sections of the new site now completed.
1.1.2 Considerable time and care is being spent to ensure that the pages are easy for residents to navigate and that digital transactions are simple. We are also ensuring that content complies with the latest regulations on accessibility for council websites.
1.1.3 Following a review of the timetable, a number of factors have led us to believe that it would be prudent to defer the launch date by approximately two months. These factors include:
The need for a ‘content freeze’ on the existing website which would create problems with publishing material relating to local and crime commissioner elections in May
The potential for teething issues with the new site and public complaints on the eve of an election
Finance,Inv&PropertyAB-NKD-Part 1 Public 06 January 2021 3
Operational requirements associated with the Covid pandemic, the cancellation of Local Plan hearings and Boundary Review which together are limiting staff time to provide the necessary support with content migration
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Finance, Innovation and Property Advisory Board at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.