Resolved
RESOLVED : That the virement of £150,000 from the mandatory DFG budget for the 2023/24 financial year to the discretionary DFG budget on the Capital Plan be approved.
Council approved this item on Tuesday 24 October 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the virement of £150,000 from the mandatory DFG budget for the 2023/24 financial year to the discretionary DFG budget on the Capital Plan be approved.
The Council has five cases where the cost of the mandatory Disabled Facilities Grant eligible adaptation works exceed the limit of £30,000 and in accordance with the Council’s adopted Housing Assistance Policy a discretionary Disabled Facilities Grant can be approved to top-up the mandatory DFG by up to a maximum of £30,000 to allow the adaptation works to proceed. Within the Council’s Capital Plan for 2023/24 there is no spend allocated to the Discretionary Disabled Facilities Grant budget. This report seeks Council approval for a virement of £150,000 from the mandatory to the discretionary Disabled Facilities Grant budget.
1.2.1 Funding for all Disabled Facilities Grants (DFGs), mandatory and discretionary, comes from the Better Care Fund, which is awarded to the Council by the Department for Levelling Up, Housing and Communities (DLUHC) to fund adaptations to enable disabled persons to live healthily and independently or with family members in their household in their own homes.
1.2.2 DLUHC guidance on DFG delivery states “where an authority has a locally published Housing Assistance Policy under the Regulatory Reform (Housing Assistance) (England & Wales) Order 2002, authorities do have discretion to top up amounts above the DFG £30,000 limit per applicant. Where an authority has not used this discretion within their policy they will still need to give due consideration to exceptional cases”.
1.2.3 The Council already have an adopted Housing Assistance Policy published in November 2022, which includes a discretionary DFG for topping up those mandatory DFG amounts of £30,000 by up to a further maximum of £30,000 where extensive adaptation works are needed.
1.2.4 The five cases the Council is currently processing where works are above the £30,000 threshold are for children. It is important to note that the works being
Council - Part 1 Public 24 October 2023 2
carried out fall under the mandatory element of DFG work and have been assessed as being necessary and appropriate to meet the needs of the disabled occupant, and that it is reasonable and practicable to carry out the relevant works having regard to the age and condition of the dwelling. Other sources of funding for these works will have been explored and also other housing options e.g. moving home considered before the discretionary top-up is utilised.
1.3Legal Considerations
1.3.1 The Council has a mandatory duty to deliver adaptations through the Disabled Facilities Grant scheme under the provisions of the Housing, Grants Construction and Regeneration Act 1996. Whilst it is able to offer additional discretionary assistance as provided for in the Regulatory Reform (Housing Assistance) (England and Wales) Order 2002, such discretionary schemes must not disadvantage a person eligible to receive assistance under the mandatory scheme and the Council is required to publish a Policy on how it intends to use the powers under the Regulatory Reform (Housing Assistance) (England and Wales) Order 2002 to provide housing assistance.
1.4Financial and Value for Money Considerations
1.4.1 The mandatory DFG budget for 2023/24 is £2,203,000 which is funded from the Better Care Fund and roll over from previous years. Spend to date on mandatory DFGs and commitment in 2023/24 is £920,000 however not all commitment may realise into actual spend within the year due to contractor availability/applicant choices etc. There is no spend allocated to the discretionary DFG budget. It was agreed by the Council in 2016 the budget for such discretionary DFG works in any one year will be limited to the amount by which the grant allocation, exceeds the budgeted mandatory DFG spend. I can confirm that proposed budget for discretionary DFG spend in this report is within the terms previously agreed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Disabled Facilities Grant FundingReport | 208 KB | DownloadRead as text |
Follow Council at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | MinutesThat the of the proceedings of the meeting of the Council held on 14 July 2026 be approved as a correct record and si... | Approved | Open |
| 3 Sep 2026 | Scheme of Allowances - Special Responsibility Allowances for Chair/Vice-Chair of Planning CommitteeRESOLVED : That (1) the Special Responsibility Allowance payable to the Chair of the Planning Committee be set at £5,... | Agreed | Open |
| 3 Sep 2026 | Changes to Committee Appointments 2026/27RESOLVED : That Cllr L Chapman replace Cllr R Dalton as a Conservative appointment to the Planning Committee for the ... | Decided | Open |
| 3 Sep 2026 | Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted. | Approved | Open |
| 3 Sep 2026 | Treasury Management Performance Update and Annual Report for 2025/26RESOLVED : That (1) the action taken by Officers in respect of Treasury Management activity for April to May 2026 be ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.