Resolved
RESOLVED : That the Options Appraisal Report on Sustainable Temporary Accommodation Delivery by Altair, attached at Annex 1, be noted and endorsed.
Council noted this item on Tuesday 20 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : That the Options Appraisal Report on Sustainable Temporary Accommodation Delivery by Altair, attached at Annex 1, be noted and endorsed.
1.1.1 The action plan from consultancy advice on Temporary Accommodation (TA) in early 2022 included an action on TA procurement approach as the cost of placing households in TA remains high, primarily due to the ongoing use of nightly paid accommodation for the majority of provision. The consultancy work advised a ‘natural level’ of TA need to be 80-100 placements.
1.1.2 At the time of the TA consultancy report in January 2022 the peak number of households in TA was 164 and in November 2022 had reduced to 97. There are 118 households in TA currently (November 2023) with nightly rates at an average of £50.26 in 2023/4, a 5.2% increase from the average nightly cost of placements in 2022/23.
1.1.3 With actions implemented on managing the numbers of households in temporary accommodation our focus is now on managing the cost of TA provision through reducing the cost of each placement to reduce revenue spend.
1.1.4 The Housing Portfolio Approach OSG formed in May 2023 with the purpose to carry out work to ensure TMBC makes best use of its assets to support its statutory housing functions and alleviate housing pressures in the borough. The
HPSSC-NKD-Part 1 Public 14 December 2023 2
group aims to oversee a reduction in the net cost of temporary accommodation provision.
1.1.5 Altair were commissioned to research and report on sustainable TA delivery options and the final report is presented to Members for information (Annex 1). The aim of the project was to research and investigate options for sustainable temporary accommodation provision, specifically developing an initial assessment of options and recommendations for direct delivery, such as commissioning delivery of units on council land using Modern Methods of Construction (MMC), long lease options and property acquisition to secure approximately 40 units of temporary accommodation in borough. The 40 units could be achieved through a combination of options.
1.1.6 The Temporary Accommodation Portfolio Action Plan (Annex 2) sets out range of actions over the next five years aiming to improve TA provision and reduce revenue expenditure on TA.
1.2The Council’s existing TA portfolio and costs
1.2.1 The Council’s TA portfolio currently consists of;
6 self-contained units in Tonbridge 8 HMO units and 2 houses in Tonbridge 7 self-contained studio units at in Maidstone, utilised for 1 bed need households with more complex needs 9 Clarion properties (this number fluctuates and can be up to 20 depending on conversion to permanent tenancies, move on options and suitability/availability of new properties) Remainder of households placed in nightly paid TA.
1.2.2 Current expenditure of TA provision, primarily through nightly paid provision is summarised in the table below, with spend for last financial year 2022-23 being £1,628,290 with a net cost of £748.14 to the Council:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Options Appraisal Report 24/12Appendix 1 | 6.3 MB | Download |
PDF |
Report of Director of Planning, Housing and Environmental Health 24/12Report | 512 KB | DownloadRead as text |
PDF |
Sustainable Temporary Accommodation Options Report and Temporary Accommodation Provision Action PlanReport | 8 KB | Download |
Follow Council at Tonbridge and Malling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | MinutesThat the of the proceedings of the meeting of the Council held on 14 July 2026 be approved as a correct record and si... | Approved | Open |
| 3 Sep 2026 | Scheme of Allowances - Special Responsibility Allowances for Chair/Vice-Chair of Planning CommitteeRESOLVED : That (1) the Special Responsibility Allowance payable to the Chair of the Planning Committee be set at £5,... | Agreed | Open |
| 3 Sep 2026 | Changes to Committee Appointments 2026/27RESOLVED : That Cllr L Chapman replace Cllr R Dalton as a Conservative appointment to the Planning Committee for the ... | Decided | Open |
| 3 Sep 2026 | Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted. | Approved | Open |
| 3 Sep 2026 | Treasury Management Performance Update and Annual Report for 2025/26RESOLVED : That (1) the action taken by Officers in respect of Treasury Management activity for April to May 2026 be ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.