CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Tonbridge and Malling Borough Council
Council, Tuesday 12 May 2026 at 7.30pm

Programme of Meetings 2026-28

Approved Committee 5 papers

AI summaryTonbridge and Malling Borough Council has adopted its programme of meetings for 2026/27 and a provisional programme for 2027/28, choosing Option B which sets a single planning committee meeting monthly on Wednesdays.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedProgramme of meetings for 2026-2028
MoneyNot stated
What happens nextEffective immediatelyWill go on council website soon
Who it affectsMembers and officersPlus residents viewing livestreams

What was decided

The Council adopted the programme of meetings for 2026/27 and the provisional programme for 2027/28 as set out in Annexes 1 and 2, Option B.

Option B reflects a single planning committee meeting monthly on a Wednesday. Report 5.3, 5.4

The adopted programme is effective immediately. Report 11.1

Why

It is the responsibility of the annual meeting of the Council to approve a programme of meetings for the coming year. Report 4.1, 9.2

Option B was selected because elsewhere on the agenda the Council considered planning committee reforms under the Planning and Infrastructure Act 2025, which if approved would require a single planning committee meeting monthly. Report 5.2, 5.3

Holding the single planning committee on a Wednesday provides greatest flexibility and operational control for Development Management and Democratic Services. Report 5.4

What happens next

The programme will be available on the Borough Council's website as soon as possible. Report 11.1

Any additional meetings required will be set up in consultation with the relevant Chair, the Leader and Cabinet Member. Report 4.5

Democratic Services will continue to review the cycle for committees with services to ensure an even spread of meetings where possible. Report 4.6

Options considered

  • Rejected: Option A: programme of meetings for 2026-2028 as approved by Council on 21 April 2026. Council chose Option B to reflect possible planning committee reforms under the Planning and Infrastructure Act 2025 Report 4.4, 5.1, 5.2, 5.3
  • Chosen: Option B: alternative programme reflecting a single planning committee meeting monthly on a Wednesday. Provides greatest flexibility and operational control for Development Management and Democratic Services; aligns with potential planning committee reforms Report 5.3, 5.4

Implications

  • Risk: Risk that the meeting programme is subject to change during 2026-2028 as a consequence of elections, local government reorganisation and any unforeseen circumstances. Report 8.5
  • Legal: The programme meets the legal duty to hold the annual meeting during March/April/May and to calculate the council tax requirement by 11 March. Report 9.1
  • Equalities: The council operates a hybrid model of meetings and meetings are livestreamed, giving residents greater access to see how decisions are made.
  • Climate: Limited impact on emissions and environment; the council uses a paper light, moving to paperless, approach with agendas online and via Member iPads.
  • Risk: Without a programme in place, the Borough Council's ability to take decisions in a timely manner could be affected. Report 4.3, 8.1
  • Staffing: Use of venues and equipment at Kings Hill is supported by the Health and Safety Officer, Head of Administration and Property, and Head of IT, who ensure safety checks are undertaken. Report 8.3

Who and where

  • Members (councillors), for diary management and statutory notice deadlines Report 8.2, 9.1
  • Management Team, Senior Officers and Cabinet Members, consulted on the proposed dates Report 10.1
  • Democratic Services and Development Management staff Report 4.6, 5.4
  • Residents viewing meetings via livestream or attending online

Timeline

  • 8 April 2025: Detailed report on meeting programme communicated to all councillors Report 10.1
  • 21 April 2026: Council approved the programme to go forward to Annual Council for adoption Report 4.2, 5.1
  • 12 May 2026: Annual Council adopted the programme of meetings (Option B)
  • 2026-2028: Programme period covering 2026/27 and provisional 2027/28 Report 8.5

Plain English for the jargon

  • Option A: The programme of meetings for 2026/27 and provisional 2027/28 as approved by Council on 21 April 2026.
  • Option B: An alternative programme reflecting a single planning committee meeting monthly on a Wednesday.
  • Annual Council: The annual meeting of the Council, held during March, April or May, responsible for approving the programme of meetings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC 26/58

Resolved

RESOLVED : That the programme of meetings for 2026/27 and the provisional programme of meetings for 2027/28 (as set out at Annexes 1 and 2 – Option B to the report) be adopted.
Word for word from the decision Tonbridge and Malling published for this meeting. Source: democracy.tmbc.gov.uk

Follow this further

Built from Tonbridge and Malling's papers

What the report saysPro

Report to Council

Recommendations

3.1That the Programme of Meetings for 2026-2028 be approved in accordance with Members’ preference for Option A or Option B, as set out in Annexes 1 and 2.

4 Introduction and Background

4.1It is the responsibility of the annual meeting of the Council to approve a programme of meetings for the coming year.

4.2The programme of meetings was approved by Council on 21 April 2026 to go forward to the meeting of Annual Council for adoption.

4.3There are a number of factors to be taken into account when preparing a programme of meetings. The aim is to allow Annual Council to approve a schedule which is fixed for the upcoming municipal year, whilst recognising the need to respond to specific and changing circumstances. If a programme was not

Cou P1-Public 12 May 2026 2

in place the Borough Council’s ability to take decisions in a timely manner could be affected.

4.4There were no changes recommended by Members to be made and the final programme is attached at Annexes 1 and 2 (Option A) for adoption.

4.5Any additional meetings required to be made to the programme will be set up in consultation with the relevant Chair, the Leader and Cabinet Member.

4.6Democratic Services will continue to review the cycle for Committees with Services to ensure an even spread of meetings where possible throughout the year.

5 Proposal

5.1The programme of meetings for 2026-2028 as approved by Council on 21 April 2026 is presented for adoption and is set out as Option A.

5.2Elsewhere on the agenda, the Council will consider the implementation of planning committee reforms under the Planning and Infrastructure Act 2025. If these reforms were approved and a single planning committee introduced changes would be required to the programme of meetings as presented.

5.3An alternative programme of meetings reflecting a single planning committee meeting monthly is set out as Option B.

5.4Having the single planning committee meet on a Wednesday provides greatest flexibility and operational control for Development Management and Democratic Services purposes.

6 Other Options

6.1There were no other significant options considered as the framework for Borough Council meetings already exists.

6.2However, consideration was given to avoiding scheduling meetings during school holidays. Whilst this is not practical given the number of meetings to be held small changes have been made where possible to accommodate this request.

7 Financial and Value for Money Considerations

7.1The use of external venues, audio/visual equipment and livestreaming facilities incurs some expenditure arising from room and equipment hire, some of which can be significant.

Cou P1-Public 12 May 2026 3

8 Risk Assessment

8.1There is a risk that the implementation of decisions and/or outcomes could be delayed if there wasn’t a programme in place and a meeting couldn’t be scheduled at short notice, either due to a venue or Members being unavailable.

8.2It is much more practical for Members in terms of diary management to have a programme in place for the municipal year. This also ensures that all statutory deadlines in respect of publishing notices of meeting and agendas are met.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OPTION A 2026-27 Approved Programme with Revisions (Notes) (1) 26/58Appendix 1 671 KB Download
PDF
OPTION B 2026-27 Approved Programme with Revisions (Notes) 26/58Appendix 1 668 KB Download
PDF
OPTION A 2027-28 DRAFT Programme 26/58Appendix 2 666 KB Download
PDF
OPTION B 2027- 28 DRAFT Programme 26/58Appendix 2 662 KB Download
PDF
Programme of Meetings 2026-28Report 153 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

42 of 44 attended
CB
Councillor Christopher BrownChair, present
KT
Councillor Kim TannerVice-Chair, present
LA
Councillor Lee AthwalCommittee Member, present
BB
Councillor Bill BanksCommittee Member, present
KB
Councillor Kath BartonCommittee Member, present
MS
Councillor Mrs Sue BellCommittee Member, present
AB
Councillor Angus BennisonCommittee Member, present
RB
Councillor Robin BettsCommittee Member, present
TB
Councillor Timothy BishopCommittee Member, apologies
MB
Councillor Matt BoughtonCommittee Member, present
PB
Councillor Paul BoxallCommittee Member, present
GB
Councillor Garry BridgeCommittee Member, present

All 44 on the meeting page

On this subject at Tonbridge and Malling

Search all
  1. Programme of Meetings 2026-28This decision
  2. Programme of Meetings 2026/27 and 2027/28Approved
  3. Programme of MeetingsApproved
  4. Programme of Meetings 2025 - 2027Approved
  5. Programme of MeetingsApproved
  6. Programme of Meetings 2024-25 and 2025-26Approved

More from Tonbridge and Malling Council

All decisions
MeetingDecisionOutcome
3 Sep 2026 MinutesThat the of the proceedings of the meeting of the Council held on 14 July 2026 be approved as a correct record and si... Approved Open
3 Sep 2026 Scheme of Allowances - Special Responsibility Allowances for Chair/Vice-Chair of Planning CommitteeRESOLVED : That (1) the Special Responsibility Allowance payable to the Chair of the Planning Committee be set at £5,... Agreed Open
3 Sep 2026 Changes to Committee Appointments 2026/27RESOLVED : That Cllr L Chapman replace Cllr R Dalton as a Conservative appointment to the Planning Committee for the ... Decided Open
3 Sep 2026 Local Code of Corporate GovernanceRESOLVED : That the updates and amendments to the Local Code of Corporate Governance (Annex 1) be approved and adopted. Approved Open
3 Sep 2026 Treasury Management Performance Update and Annual Report for 2025/26RESOLVED : That (1) the action taken by Officers in respect of Treasury Management activity for April to May 2026 be ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies