Internal Overview & Scrutiny, Tuesday 9 August 2016 at 2.00pm

Bridge Buildings Options

Decided Scrutiny 6 papers

Internal Overview & Scrutiny decided this item on Tuesday 9 August 2016. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

That Internal O&S Committee recommend to the C&R Committee that the Council market the site for a freehold or leasehold disposal at the earliest opportunity in order to move the project forward with no obligation by the Council to accept any offer. (Vote: For – Unanimous) It was proposed by Councillor Langmead, seconded by Councillor Hackett and – That the meeting return to Part I and that any press and public be readmitted. (Vote: Unanimous) DATE OF NEXT MEETING The Chair confirmed that the next Overview & Scrutiny (Internal) Committee meeting would be held on Tuesday 27 September 2016 at 4.00 pm.
Word for word from the decision Torridge published for this meeting. Source: democracy.torridge.gov.uk

Follow this further

Built from Torridge's papers

What the report saysPro

Report to Internal Overview & Scrutiny

REPORT OF Senior Solicitor To: Internal Overview & Scrutiny Committee Subject: Bridge Buildings Options Date: 9 August 2016 Reference:

Confidential or Exempt Information - Not for Publication by virtue of Paragraph 3 of Part 1 and Paragraph 10 of Part 2 of Schedule 12A of the Local Government Act 1972.

PURPOSE OF REPORT: To recommend to C&R the preferred Option for the future of Bridge Buildings, Bideford

1. INTRODUCTION

As part of the approved Transforming Torridge Project (TTP) the Council is restructuring its Office Accommodation to achieve greater efficiencies and better facilities for the reduced number of staff and better public access to services. This summary includes:

 A New Customer Hub at RBH.  New Offices at RBH.  Relocation of the Server Suite to RBH.  Use of the Town Hall as a Training and Meeting Location complete with Member Facilities and use with other Public Sector Bodies.  Investment and Refurbishment in Facilities e.g. extra PV at RBH, new sound system etc.

Also under the Asset Management Plan, the stated aim is an ongoing move in the shape of the estate to make it more closely fit our Strategic aims, service delivery and to improve efficiency and income generation.

This report is to update Committee with the options for Bridge Buildings, which will become vacant in late 2017 when staff relocates to RBH. In the TTP the stated intention was to generate savings of £141k from office accommodation changes. This report outlines further investigations and discussions with the Income Generation Working Group.

2. REPORT

There are clearly a number of Options regarding Bridge Buildings. The original TTP Option that was agreed was it be vacated and marketed or disposal or rent. The basis being as revenue savings of approx. £70,000 pa and Planned Maintenance averages out to about £8,000 pa (the last externals was 2013 at the cost of £76,000 with Internals in 2011 of £17,000 plus ad hoc items ongoing) The anticipated Capital Receipt would in in the order of £350,000 - £400,000, which is subject to a number of variables e.g. use. Clearly this value can appear low at first site, but it is for a commercial property and takes into account the building condition, conversion costs, running costs, opportunities, location etc.

As previously stated Bridge Buildings has provided very good service provision to the Council after its investment in the Building to refurbish in the late 1990s, however, it suffers from a poor and inefficient internal layout driven by its existing 1880s layout and construction. Hence GIA/NIA efficiency (i.e. effective usable space) is 51% against good practice of +80%, most first and second floor windows cannot be opened due to noise, pollution and fire safety factors, the centralised air handling system struggles in hot weather (which results in staffing issues), Teams are disjointed by the cellular layout, the site is restricted on all four sides and hence access is difficult, and parking is remote from the site. The condition of the exterior of the property continues to be of concern with the local stone known to be very sandy in areas and prone to lamination, hence the stone replacement; pining and lime-washing that is undertaken. Clearly though it does benefit from a good central location and has provided good facilities for several years for the Councils needs over that period.

There are clearly other options such as:

 Leasehold disposal i.e. we lease the building out either in whole or part, with or without refurbishment or conversion and as either a let or managed facility  Conversion to other uses e.g. residential and either disposal with permission or use as a managed rented facility. These would require Planning approval and various reports e.g. flooding so would represent expenditure to obtain.  Land Bank  An owner occupier use e.g. a National chain type use i.e. the “wetherspoons” approach.  Disposal to third party partner e.g. Town Council etc.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 207 KB Download
PDF
Appendix 2Appendix 2 319 KB Download
PDF
Appendix 3Appendix 3 15 KB Download
PDF
Appendix 4Appendix 4 87 KB Download
PDF
Appendix 5Appendix 5 4.9 MB Download
PDF
Bridge Buildings OptionsReport 104 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 16 attended
PW
Councillor Peter WatsonChair, present
PL
Councillor Peter Le MaistreVice-Chair, present
AD
Councillor Anna DartCommittee Member, apologies
GD
Councillor Gaston DezartCommittee Member, absent
PH
Councillor Philip HackettCommittee Member, present
ML
Councillor Mervyn LangmeadCommittee Member, present
PP
Councillor Philip PenningtonCommittee Member, present
CS
Councillor Cathrine SimmonsCommittee Member, present
AW
Councillor Alan WhittleCommittee Member, present
SH
Steve HearseOfficer, in attendance
DH
David HeyesOfficer, in attendance
JH
Jamie HollisOfficer, expected

All 16 on the meeting page

On this subject at Torridge

Search all
  1. Bridge Buildings OptionsThis decision
  2. Bridge BuildingsApproved

More from Torridge Internal Overview & Scrutiny

All decisions
MeetingDecisionOutcome
21 Jul 2026 MinutesThat the minutes of the meeting held on the 28 th April 2026 be agreed and signed as a correct record. (Vote: For – 9... Agreed Open
28 Apr 2026 MinutesThat the minutes of the meeting held on 17 th March 2026 be agreed and signed as a correct record. (Vote: For 7, Abst... Agreed Open
17 Mar 2026 MinutesThat the minutes of the meeting held on the 10 th February 2026 be agreed and signed as a correct record. (Vote: For ... Agreed Open
10 Feb 2026 MinutesThat the minutes of the meeting held on the 2 nd December 2025 be agreed and signed as a correct record. (Vote: For –... Agreed Open
10 Feb 2026 Capital Programme 2026/27 - 2030/31That the following recommendations be approved, and recommended to Full Council: a) The Capital Programme is updated ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies