Resolved
That the application be refused for the reasons as stated above. (Voted: For 7, Against 1)
Plans Committee refused this item on Thursday 7 June 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the application be refused for the reasons as stated above. (Voted: For 7, Against 1)
Members will recall that this application was considered at the Plans Committee on 10th May 2018 where it was resolved that the Committee was minded to refuse the application.
In accordance with the Committee’s Terms of Reference, in the event Members are minded to approve or refuse an application contrary to the recommendation in the report, the item shall be deferred for a further report to be presented to Committee. This sets out the implications, process and risks and shall be considered before the final decision is taken.
Reasons for Refusal
The draft minutes note that Members were minded to refuse the proposal as “the application does not comply with DVT2C, DVT24, parking issues and impact on the environment”. There was, however, no specific harm identified by Members in relation to these matters when the resolution was put and seconded.
In respect of the reference to ‘parking issues’, much of the consideration of this application focused on the provisional refusal of the previous application for the car park with Members questioning whether a car park could be provided within the development site. Both the Principal Planning Officer and the Senior Solicitor confirmed as the proposed Section 106 Heads of Terms included a requirement for land to be provided for a car park then the fact the previous application had been provisionally refused would not be a robust basis for refusing this application. The Highway Officer addressed the concerns raised by Members, in particular the comments with regard to the previous car park application which had provisionally been refused.
The Highway Officer has since further clarified that his previous responses set out that a car park and other mitigation including bus contribution is required to mitigate the impact of the proposal. The spine road through the site giving two access points, a car park, the contribution and all other requirements can be secured through a legal agreement and reserved matters permission -adequately mitigating the impacts of the proposal. The need for a car park arises from the need for mitigation of the issues of illegal and dangerous parking around the school. There is a need for ‘a’ car park on the site, not necessarily ‘the’ car park in application 1/0702/2017/OUT.
The Highway Officer has confirmed that refusal of the application on highway grounds would be contrary to NPPF paragraph 32 being as there is no evidence to show that the impact of this proposal would be severe if the developer delivers the items that can be secured through planning conditions and/or a legal agreement on the site or on land off site in their control. In any event, Members gave no policies in their resolution that relate to parking so it is not considered that a robust refusal reason can be recommended.
The draft minutes indicate that Members also referred to the sewerage problems in Great Torrington and felt that if this application was to be approved there would be a need for the system to be updated. This is consistent to the reference to the proposal being contrary to Policy DVT24.
Policy DVT24: Sewerage and Drainage, states:
(1) Development will be permissible in unsewered areas where it is to be provided with adequate means of foul and surface water drainage and where there will be no unacceptable risk:
(a) of off-site flooding or increased flood risk; or (b) to the quantity and quality of potable groundwater sources or private water supplies.
(2) In areas served by mains sewers, planning permission for the use of septic tanks or cesspools will not be granted.
(3) Development will be permitted in areas of sewerage infrastructure deficiency only where:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Application 1/0246/2017/OUTMReport | 213 KB | DownloadRead as text |
Follow Plans Committee at Torridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jul 2026 | Application No. 1/0001/2026/FULMResolved – That the ... view the full minutes text for item 288. | Decided | Open |
| 30 Jul 2026 | Application No. 1/0386/2026That the application is approved subject to the conditions outlined in the report. A recorded vote was taken. COUNCIL... | Approved | Open |
| 30 Jul 2026 | Application No. 1/0258/2026/FULThat the application be approved, with an informative added for solar, rainwater capture and heat pump provision. A r... | Approved | Open |
| 30 Jul 2026 | Planning DecisionsResolved - That the Planning decisions for the period 23 rd June 2026 – 15 th July 2026 be noted. | Noted | Open |
| 2 Jul 2026 | Planning DecisionsResolved - That the Planning decisions for the period 20/5/2026 – 23/6/2026 be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.