CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Torridge District Council
Community & Resources, Monday 16 July 2018 at 6.30pm

Old Cattle Market Buildings - Demolition

Noted Committee 1 paper

Community & Resources noted this item on Monday 16 July 2018. Below is the council's own wording, with the papers it was decided on.

Item28

Resolved

a) That the process( es ) required to be followed to enable a legal demolition of the old Cattle Market buildings to take place be noted b) That the progress made to date to facilitate as early as possible the demolition be noted c) That the demolition of the Cattle Market building as proposed in the report and in light of the resolution of Full Council at its meeting of the 18 June 2018, be approved d) That the submission of a “prior planning application” for notification of the proposed demolition of the old Cattle Market Buildings be approved e) That the virement of additional funds (should the costs exceed £78,000) from the Regeneration Capital Allocation (£1.5m Budget) as necessary (cannot exceed £100,000 as a Full Council decision would be required) be approved. a) That the process( es ) required to be followed to enable a legal demolition of the old Cattle Market buildings to take place be noted b) That the progress made to date to facilitate as early as possible the demolition be noted c) That the demolition of the Cattle Market building as proposed in the report and in light of the resolution of Full Council at its meeting of the 18 June 2018, be approved d) That the submission of a “prior planning application” for notification of the proposed demolition of the old Cattle Market Buildings be approved e) That the virement of additional funds (should the costs exceed £78,000) from the Regeneration Capital Allocation (£1.5m Budget) as necessary (cannot exceed £100,000 as a Full Council decision would be required) be approved. (Vote: For – Unanimous)
Word for word from the decision Torridge published for this meeting. Source: democracy.torridge.gov.uk

Follow this further

Built from Torridge's papers

What the report saysPro

Report to Community & Resources

REPORT OF Strategic Manager (Resources) To: Community & Resources Subject: Old Cattle Market Buildings – Demolition Date: 16 July 2018 Reference:

PURPOSE OF REPORT: To report to Members the processes required to be followed to proceed with the demolition of the old Cattle Market Buildings as proposed by Full Council on 26 June 2018

1. INTRODUCTION

At Full Council on 18 June 2018 a question was submitted by Councillor Brenton under Procedural Rule A9 and was debated by Members following the suspension of the Council’s Standing Orders.

“Why the buildings at the Old Cattle Market Bideford are not demolished bearing in mind that the roofs are asbestos and broken, and that the site is not secure enough to stop people gaining access?”

Following a debate Members approved that:

“The old Cattle Market buildings are demolished to make the area safe”

The decision itself as approved was reached in the absence of it being an item on the published agenda with a report setting out the details and implications of the course of action proposed, which would provide Members with the information necessary to make an informed decision.

Making a decision in such a way could open the Council to the risk that illegal decisions are taken and or subject to legal challenge. This report therefore sets out for Members the steps required to achieve the demolition of the buildings on the site

2. REPORT

At Full Council on 18 June 2018 Members debated and approved the proposal to demolish the TDC owned buildings on the old Cattle Market Site Bideford, which aside from its partial use as storage have remained largely redundant since the operation as a Cattle Market ceased in 2005.

As background there is a wider strategic development aspiration for the site and the surrounding area for a leisure led project. The specific details of what that might include have yet to be fully established and or approved by Members. One of the main reasons for the demolition work to have not progressed far as yet is due to the overall project was forecast to be funded from S106 contributions attributable to developments that have yet to commence on site and therefore the actual resources could be some years away yet.

However, the master-plan was to incorporate the demolition and clearance of the cattle market site as part of the overall development and therefore the costs of demolition would be met within the scope of that project and the budget..

Despite that there is a sum of £78,000 allocated within the Council’s Capital Programme for 2018-19 as an estimate of the costs of demolition. The reason being that consideration was given to whether the works should or might be required to be done earlier e.g. for Health and Safety reasons. Although to date and currently the site has been securely fenced off with appropriate signing warning the public not to enter.

At Full Council on 18 June 2018 the timing of implementing this decision was discussed however, in the absence of a report setting out the necessary and legal process for undertaking the work officers were unable to provide any details..

The following paragraphs explain the steps that we need to follow in order to demolish the buildings in compliance with applicable legislation.

 Planning Requirements

A “prior planning application” for notification of proposed demolition is required to be submitted, which identifies the specifics of the demolition proposed i.e. plans, drawings, etc. and also what reinstatement works are proposed such as fencing.

Cost £80

 Building Regulations Requirements

Any person who intends to carry out the demolition of a building must inform the Local Authority in writing. Legally, no one can start demolition work unless the Local Authority has been notified. The notification must specify the building to which it relates and the work of demolition intended to be carried out, but this is not required to be set out on a special form.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Old Cattle Market Buildings: DemolitionReport 99 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 29 attended
DH
Councillor David HurleyChair, present
AD
Councillor Anna DartVice-Chair, present
DB
Councillor David BrentonCommittee Member, present
CC
Councillor Cheryl Cottle-HunkinCommittee Member, present
KD
Councillor Kenny DavisCommittee Member, present
PH
Councillor Philip HackettCommittee Member, present
RH
Councillor Robert HicksCommittee Member, present
JH
Councillor John HimanCommittee Member, present
RL
Councillor Rosemary LockCommittee Member, present
DM
Councillor Dermot McGeoughCommittee Member, present
JW
Councillor Jane WhittakerCommittee Member, present
RW
Councillor Richard WisemanCommittee Member, present

All 29 on the meeting page

More from Torridge Community & Resources

All decisions
MeetingDecisionOutcome
7 Sep 2026 Minutes of the Community & Resources Committee meeting held on 13th July 2026Resolved: That the Minutes of the meeting held on 13 th July be signed as a correct record. (Vote: For – 10, Against ... Decided Open
7 Sep 2026 Agreement of Agenda between Parts I and IIResolved: That the Agenda as circulated be agreed. (Vote: For – unanimous) Agreed Open
7 Sep 2026 Housing Enforcement PolicyRESOLVED: That the amended Housing Enforcement Policy be adopted. (Vote: For – 11, Against – 0, Abstentions - 1) Coun... Approved Open
7 Sep 2026 Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad... Agreed Open
7 Sep 2026 Exclusion of the PublicRESOLVED: That the public be excluded from the remainder of the meeting because of the likely disclosure of exempt in... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies