CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Torridge District Council
Community & Resources, Monday 22 March 2021 at 4.00pm

The Burrows Centre - Changing Places Facility

Approved Committee 1 paper

Community & Resources approved this item on Monday 22 March 2021. Below is the council's own wording, with the papers it was decided on.

Item116

Resolved

That the inclusion of the Changing Places facility within the costs included in the original contract sum and remaining contingency sum for the completion of this element of the building as part of the overall project be approved. That the inclusion of the Changing Places facility within the costs included in the original contract sum and remaining contingency sum for the completion of this element of the building as part of the overall project be approved. A recorded vote was taken. COUNCILLOR FOR AGAINST ABSTAIN Brenton, D Bright, C X Bushby, D X Christie, P X Dart, A X Hicks, R X Hutchings, J X James, K X Laws, N X Lock, R X McGeough, D X Wiseman, R X Councillor Brenton was not present for the vote. (Vote: For 10, Against 1)
Word for word from the decision Torridge published for this meeting. Source: democracy.torridge.gov.uk

Follow this further

Built from Torridge's papers

What the report saysPro

Report to Community & Resources

Purpose of report

To seek Member approval for the use of the project contingency funds for the completion of the Changing Places facility as part of the Visitor Centre completion.

1.0Introduction

At the Communities and Resources Meeting of 7th September 2020, Members approved the progress of the new Visitor centre with a series of recommendations. Recommendation 5. outlined the following: To deliver the revised scheme within the grant funding limits available and to return to Members with details of any further contribution that may be required from within the capital budget already approved. The purpose of this report is to update Members on progress with the provision of the Changing Places area and to seek approval to commit the allocated project funds and remaining project contingency sum to the completion of the facility.

2.0Report Considerations The Visitor Centre element of the project is currently being delivered on programme and within budget.

The original intention was to deliver the building within the grant funding available through the CCF with the expectation that further grant opportunities would also be available for the Changing Places facility. At the time of writing this report grant funds for this element are not available and we therefore need to obtain approval for the commitment of further funds to complete this part of the project. A new funding stream will be released in future and we have already registered an interest, but this will not be available in the time that we need to complete the project.

1 We have considered deferring the Changing Places part of the project, but this is an integral part of the overall scheme and would cost proportionally more if we returned to complete this element later – assuming that additional funding could be secured for this location.

We included the actual cost of the Changing Places installation within the schedule of works for the project so that it was defined in terms of time and cost at tender stage. The value of these works are included within the contract sum, which are within the overall CCF Grant limit of £1.2m We acknowledge however that we require Member approval to commit to the spend involved for this facility if we are unable to source alternative grant funding.

The project is progressing well and at the beginning of March was on programme and within the contract sum for the works. There have been modest variations required throughout the course of the works that have involved a draw down on the contingency sum within the contract. At the time of writing the contingency sum remains in credit. At the time of writing the contingency sum remains in credit. The relevant values are summarised as follows:

• Contract Sum £ 698,927.85 which includes • Changing Places £ 27,101.40 • Contingency Sum £ 11,600.00

We therefore seek Member approval for the completion of the Changing Places facility utilising the costs included within the original contract sum and remaining contingency.

Summary

The Northam Burrows Visitor Centre project is progressing well, remains on target and within the contract sum for the works.

A Changing Places facility was included within the original contract, but at the time of seeking tenders it was hoped that additional grant funding would be available for these works. That source of grant funding is not available at present and although new funding streams are likely to be available in future, they are not likely to be available until after this project has been completed. We cannot be certain that this location will qualify for the grant funding that will be available in the future but if the opportunity arises application will be made.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Burrows Centre: Changing Places FacilityReport 222 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 31 attended
RH
Councillor Robert HicksChair, present
DM
Councillor Dermot McGeoughVice-Chair, present
DB
Councillor David BrentonCommittee Member, present
CB
Councillor Chris BrightCommittee Member, present
DB
Councillor Doug BushbyCommittee Member, present
AD
Councillor Anna DartCommittee Member, present
JH
Councillor Jon HutchingsCommittee Member, present
KJ
Councillor Ken JamesCommittee Member, present
NL
Councillor Nick LawsCommittee Member, present
RL
Councillor Rosemary LockCommittee Member, present
RW
Councillor Richard WisemanCommittee Member, present
SH
Steve HearseOfficer, in attendance

All 31 on the meeting page

On this subject at Torridge

Search all
  1. The Burrows Centre - Changing Places FacilityThis decision
  2. The Burrows Centre - Request for Additional Funding.Decided
  3. Northam Burrows Visitors CentreDecided

More from Torridge Community & Resources

All decisions
MeetingDecisionOutcome
7 Sep 2026 Minutes of the Community & Resources Committee meeting held on 13th July 2026Resolved: That the Minutes of the meeting held on 13 th July be signed as a correct record. (Vote: For – 10, Against ... Decided Open
7 Sep 2026 Agreement of Agenda between Parts I and IIResolved: That the Agenda as circulated be agreed. (Vote: For – unanimous) Agreed Open
7 Sep 2026 Housing Enforcement PolicyRESOLVED: That the amended Housing Enforcement Policy be adopted. (Vote: For – 11, Against – 0, Abstentions - 1) Coun... Approved Open
7 Sep 2026 Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad... Agreed Open
7 Sep 2026 Exclusion of the PublicRESOLVED: That the public be excluded from the remainder of the meeting because of the likely disclosure of exempt in... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies