That before entering into a Grant Agreement with Red Earth for the use of the £797,000 LRF grant, the conditionality required by DLUHC and the One Public Estate team be put in place and the Council’s position in relation to grant claw back be protected prior to drawing down the grant. (Vote: For – 24, Abstentions – 3)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
Design: Remediation design and specification proposals were put forward by John Grimes Partnership (JGP) acting for both the Developer and the Authority.
Page |1 The initial proposals were as described by annotated JGP’s drawings: • 14466 201 P1 • 14466 202 P2 • 14466 203 P2 • 14466 204 P2 • 14466 205 P2 Drawings under separate cover. These propose several degrees of associated and related forms of remediation as noted below to the existing harbour wall of varying height of the order of 5m above the sediment layer for a length of the order of 170m with a 4m (approx.) return , namely: • Repair type 1. Catering for masonry face strengthening and replacement and fixing back to harbour wall substrata • Repair type 2. Catering for repointing and fixing back to harbour wall substrata • Harbour wall upgrade including retention via ‘dead man’ block. This is located at the optimal position whilst remaining outside the development demise. T and fixing back to harbour wall substrata that is within 7m of harbour wall. New RC Coping.
The total specification above caters for the highest of specifications without a ‘life expectancy’ benchmark being pre-set ,however JGP anticipate this to be of the order of 60 years with minimal maintenance.
The specification caters for : • Stainless steel tie backs, Grade 316 ties at 3m centres horizontally and approximately 2m vertically between ‘dead block’ and wall face with D70 H/W retaining fenders. • Stainless steel grade 316 ties with resin bond at horizontal and vertical 450mm centres. • Stainless steel joint reinforcement • Stone replacement • Marine grade grout and mortar to fill and joints • Weep pipes
Page |2 • Mass concrete ‘dead man’ block for entire length of wall section 2m x 3m deep with SS tie fixings
Construction cost. The cost to undertake the above works was ‘market tested’ with specialist contractors for each of work sections, namely civils works, stone repair and tie drilling and wall construction. The works to be undertaken under a single contract based on an agreed standard industry prime cost form due to the uncertain nature and type of works being undertaken. Budget Costs, Harbour Wall Repair. Stone wall repair: £ £ • Masonry repair 15,550.00 • Re-pointing 4,650.00 • Helical bar fixing 65,100.00 • Drill holes for grout 18,300.00 • Grouting holes 13,250.00 • Grout 45,750.00 • Weep holes 2,300.00 164,900.00
Specialist tie bars: 27mm stainless at 3m spacing per JGP specification £ • Mobilisation 7,000.00 • Horizontal ties 179,200.00 • Horizontal drainage 53,200.00 239,400.00
Page |3 • Concrete and backfills 174,300.00 • Temporary works 80,000.00 • Sundries 10,000.00 340,700.00
Fenders: D70 52,700.00 52,700.00
Total } £ 797,700.00
Scope: The scope is based on a total of 112Nº 27mm diameter stainless steel ties each 6.5m in length installed as pairs at 3m centres over the 170m wharf length together with 112Nº 4m long horizontal drains in pairs at 3m centres all as detailed on The John Grimes Partnership drawing Nº205 rev P2.
Ties The ties would consist of 27mm diameter stainless steel thread bars as specified installed with 114mm diameter permanent steel casings installed from commencement level through the existing wall and hearting material terminating in the Deadman block excavation using the ‘odex’ drilled installation system.
The horizontal drains would be drilled using the same method using slotted steel casing, with a suitable slotted plastic well liner installed as specified on completion.
No allowance is made at this stage for rotary core drilling through the face of the wall.
Installation The ties and drainage boreholes would be installed using a drilling unit mounted within a load tested working platform suspended from a suitable telescopic handler standing on the wharf. Compressed air for the drilling
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.