That the following be recommended to Full Council: a) The Capital Programme be updated to include: · Sully House · Sully House Modular Units · Hubbastone Conversion That the following be recommended to Full Council: a) The Capital Programme be updated to include: · Sully House · Sully House Modular Units · Hubbastone Conversion (Vote: For – Unanimous)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
REPORT OF Deputy Section 151 Officer To: Community and Resources Committee Subject: Capital Programme 2023/24 to 2027/28 Date: 30th January 2023 Reference:
PURPOSE OF REPORT: For Members to consider, formulate and recommend updates to the Capital Programme 2023/24 to Full Council.
The Capital Programme includes authorised projects which require updating due to inflationary pressures, along with new PIDs (Project Initiation Documents) which require authorisation from members before inclusion.
1. Introduction
1.1The Capital Programme covers the current and forthcoming five years.
It is made up of: - Approved Projects (PIDs) - New Proposed Projects (PIDs)
These are funded by: - Current Capital Reserves - Future contributions from revenue - Current/Future Capital Receipts - Current/Future Capital Grants
Previously the Council set aside 50% of its New Homes Bonus (NHB) funding into its capital program, however the level of NHB funding has been in sharp decline and is likely to cease in the near future. The decline in NHB funding has been a significant contributory factor to the increased capital funding pressures.
In addition to funding pressures, the capital programme is also under significant pressure from the increase in inflation.
1.1Capital Programme – Funding Pressures & New PIDs
Due to the funding/inflation pressures that the Council is facing, no new PIDs were sought for inclusion in the 2023/24 Capital Programme.
However projects have arisen during the year, that aim to alleviate some of the wider cost pressures the Council is under.
These Projects are: - Sully House (Approved by C&R March 2022) - Sully House Modular Units (Approved by C&R March 2022) - Hubbastone Conversion (Approved by C&R July 2022)
These projects need to be formally added to the Capital Programme. 1.2 Capital Programme – Bfwd
The brought forward balance on the Capital Programme on 1st April 2022 was:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated 22/23 25,986 (28,541) (2,555)
(See Appendix 1 for the breakdown)
1.3Capital Programme – Movements in the year
Environment Centre (updated by Full Council – December 2022)
Due to increasing costs, the environment Centre provision was adjusted, this included: - Reduced overall cost to £7.2M - Reduced borrowing to £2.8M - Various capital PIDs released, and funds reallocated to the centre - Future capital receipts earmarked for the centre
Effect on Capital Programme:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated Environment Centre 24,658 (27,213) (2,555)
Homelessness – Projects to alleviate wider cost pressures
Projects are: - Sully House £968K (Approved by C&R March 2022) - Sully House Modular Units £221K (Approved by C&R March 2022) - Hubbastone Conversion £372K (Approved by C&R July 2022)
The Capital Programme has £226K of budget remaining on the “Homelessness” PID, which was originally for £1m (with £1m of approved borrowing). To date the spend on this PID has been funded through general capital reserves.
Hubbastone uses this remaining budget (£226K) plus other identified reserves (£146K)
Sully House Modular Units have £174K grant funding, the remainder coming from capital reserves/borrowing.
Sully House – funding to come from capital reserves/borrowing
It is proposed that as the borrowing has not yet been utilised, that the approved borrowing of £1m is used for Sully House / Sully House modular, and the previous spend is funded from capital reserves. (See appendix 2 for detailed adjustments)
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated Homelessness Projects 25,993 (27,533) (1,540)
Extend Capital Programme by 1 year – For a full 5 year programme
(See appendix 2 for detail)
Updates are for extension of existing programmes:
– Car Parks / Property / IT Equip / DFGs (disabled facilities grants) / Vehicles:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.