Resolved
That t he Capital Programme be updated to include: · Sully House · Sully House Modular Units · Hubbastone Conversion (Vote: For 27, Abstentions 1)
Full Council decided this item on Monday 20 February 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That t he Capital Programme be updated to include: · Sully House · Sully House Modular Units · Hubbastone Conversion (Vote: For 27, Abstentions 1)
Agenda Item REPORT OF Deputy Section 151 Officer To: Full Council Subject: Capital Programme 2023/24 to 2027/28 Date: 20th February 2023 Reference:
PURPOSE OF REPORT: For Members to update the Capital Programme 2023/24.
The Capital Programme includes authorised projects which require updating due to inflationary pressures, along with new PIDs (Project Initiation Documents) which require authorisation from members before inclusion.
1. Introduction
1.1The Capital Programme covers the current and forthcoming five years.
It is made up of: - Approved Projects (PIDs) - New Proposed Projects (PIDs)
These are funded by: - Current Capital Reserves - Future contributions from revenue - Current/Future Capital Receipts - Current/Future Capital Grants
Previously the Council set aside 50% of its New Homes Bonus (NHB) funding into its capital program, however the level of NHB funding has been in sharp decline and is likely to cease in the near future. The decline in NHB funding has been a significant contributory factor to the increased capital funding pressures.
In addition to funding pressures, the capital programme is also under significant pressure from the increase in inflation.
1.1Capital Programme – Funding Pressures & New PIDs
Due to the funding/inflation pressures that the Council is facing, no new PIDs were sought for inclusion in the 2023/24 Capital Programme.
However projects have arisen during the year, that aim to alleviate some of the wider cost pressures the Council is under.
These Projects are: - Sully House (Approved by C&R March 2022) - Sully House Modular Units (Approved by C&R March 2022) - Hubbastone Conversion (Approved by C&R July 2022)
These projects need to be formally added to the Capital Programme. 1.2 Capital Programme – Bfwd
The brought forward balance on the Capital Programme on 1st April 2022 was:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated 22/23 25,986 (28,541) (2,555)
(See Appendix 1 for the breakdown)
1.3Capital Programme – Movements in the year
Environment Centre (updated by Full Council – December 2022)
Due to increasing costs, the environment Centre provision was adjusted, this included: - Reduced overall cost to £7.2M - Reduced borrowing to £2.8M - Various capital PIDs released, and funds reallocated to the centre - Future capital receipts earmarked for the centre
Effect on Capital Programme:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated Environment Centre 24,658 (27,213) (2,555)
Homelessness – Projects to alleviate wider cost pressures
Projects are: - Sully House £968K (Approved by C&R March 2022) - Sully House Modular Units £221K (Approved by C&R March 2022) - Hubbastone Conversion £372K (Approved by C&R July 2022)
The Capital Programme has £226K of budget remaining on the “Homelessness” PID, which was originally for £1m (with £1m of approved borrowing). To date the spend on this PID has been funded through general capital reserves.
Hubbastone uses this remaining budget (£226K) plus other identified reserves (£146K)
Sully House Modular Units have £174K grant funding, the remainder coming from capital reserves/borrowing.
Sully House – funding to come from capital reserves/borrowing
It is proposed that as the borrowing has not yet been utilised, that the approved borrowing of £1m is used for Sully House / Sully House modular, and the previous spend is funded from capital reserves. (See appendix 2 for detailed adjustments)
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme - Updated Homelessness Projects 25,993 (27,533) (1,540)
Extend Capital Programme by 1 year – For a full 5 year programme
(See appendix 2 for detail)
Updates are for extension of existing programmes:
– Car Parks / Property / IT Equip / DFGs (disabled facilities grants) / Vehicles:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s Capital Programme (2023/24) 26,856 (29,129) (2,273)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
7a: Appendix 1 -- Capital Programme BfwdAppendix | 320 KB | Download |
PDF |
7b: Appendix 2 -- Capital Programme MovementsAppendix | 411 KB | Download |
PDF |
7c: Appendix 3 -- Capital Programme by ProjectAppendix | 356 KB | Download |
PDF |
Capital Programme 2023/24 to 2027/28Report | 524 KB | DownloadRead as text |
Follow Full Council at Torridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 27 Jul 2026 | Council MinutesThat the minutes of the meeting held on the 22 nd June 2026 be confirmed as a correct record and signed by the Chair.... | Decided | Open |
| 27 Jul 2026 | Written Notice of Motion from Councillor C LeatherThat the Notice of Motion be approved. (Vote: For – Unanimous). The Motion was carried. | Approved | Open |
| 22 Jun 2026 | Council MinutesThat the minutes of the meeting held on 27 th April 2026 be confirmed as a correct record and signed by the Chair. (V... | Decided | Open |
| 22 Jun 2026 | Agreement of Agenda Items Part I and IIThat the agenda as circulated be agreed. (Vote: For, Unanimous) | Agreed | Open |
| 22 Jun 2026 | Northam Neighbourhood PlanThat Full Council: 1. Accept the recommendations of the Examiner in relation to the Northam Neighbourhood Plan, as se... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.