PID (Project Initiation Document) Project No. Cxx (office to insert) Service Development Bid for capital, ICT and asset enhancement projects
Please use this form for capital bids including ICT and asset projects over the next four years. When completed, please email to [email protected]
Revenues & Benefits Document Imaging Name of Project Project Score Process (DIPS) upgrade & conversion 85 Out of 100 Service area Revenues & Benefits Financial Score Between -20 and +20 +1 Applicant Staci Dorey Cost to Torridge over 20 years Project Start Date: Asap Saving to Torridge
Project End Date: 31.03.24 over 10 years £305,000
Section 1 – Project Details
Project Cost £75,400 + VAT External Funding
Project Summary A brief summary of the project for it to be understood by the uninitiated reader
The revenues & benefits team currently use a document imaging processing system (DIPS) for all work needing to be undertaken in order to process benefits claims & for the billing & recovery of council tax & business rates. The current product is Opentext DMS RKYV 12x which is no longer being developed & has limited support. There are no more bug fixes or development for the product. The 2012 servers used by the RKYV system stop being supported by Microsoft in November 2023. There is therefore a requirement to upgrade or move to a new system by November 2023 to remain secure & compliant.
Costs have been obtained providing the relevant details for a conversion to a new software supplier or the current product upgrade, both of which can be supported on our current Microsoft server environment.
Risks (Description of significant risks:) Climate Statement (see Section 4) Risks of not doing: Climate statement completed Y The current product is no longer being developed & the server the product „sits‟ on will Project carbon neutral Y no longer be supported effective from November 2023 which therefore puts TDC at risk of data Project works towards carbon Y breaches as neither will be secure or compliant neutral 2030
By not converting to another product the
1 incoming work will need to be kept as paper files which will need storing; this will not meet or fit in with the objectives of TDC‟s digitalisation strategy
Project detailed description The project should be described in sufficient detail for it to be understood by the uninitiated reader
The revenues & benefits team have used a document imaging system (DIPs) since 2008; this is where customer‟s incoming documents/post/e-mails etc are stored on their individual accounts/claims to enable the team to process benefit claims and bill & recover council tax and/or business rates. Prior to the implementation of DIPs the offices had walls covered with shelves which were filled with paper files. When a customer contacted the teams with regards to queries on papers, the file had to be located, retrieved and the papers viewed. Once the query had been dealt with the papers were placed in a box waiting for a clerical officer to re-file them in alphabetical order.
In light of the advancements of technology, the customers expectation of their details to be „on hand‟ and the Council‟s Strategic Plan, it is not feasible to step away from having a DIPs system.
The current product provided by Opentext is no longer being developed or supported and as from November 2023 the servers where the product „sits‟ is no longer being supported by Microsoft. Both of these situations means that TDC is at an increased risk of data breaches; staff not being able to access customers records for administration of accounts/claims or for audit purposes.
There are 2 options; either upgrade the current system or replace with a new product.
Upgrade Opentext: Implement new Capita DIPs: Migration costs £31,000 One off implementation charge £35,800 Annual licence £37,900 (already paid 23/24 ) One off licence charge £33,000 Annual maintenance £ 6,600 Total Implementation cost £31,000 £75,400
Ongoing maintenance £37,900 pa £ 6,600 pa
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies