Changes to the Contract Procedural Rules

Decided Finance 1 paper

Audit & Governance decided this item on Tuesday 16 July 2024. Below is the council's own wording, with the papers it was decided on.

Item152

Resolved

That Members recommend to Full Council the changes to the Contract Procedure Rules as referenced in this report. (Vote: For Unanimous)
Word for word from the decision Torridge published for this meeting. Source: democracy.torridge.gov.uk

Follow this further

Built from Torridge's papers

What the report saysPro

Report to Audit & Governance

Purpose of report

To agree changes to the Council’s Contract Procedure Rules following the approval of a Social Value Policy. Amendment of the Contract Procedure Rules regarding Waivers.

1. INTRODUCTION

The Council’s Community & Resources Committee on the 22 January 2024 agreed the adoption of a Social Value Policy. The Social Value Policy was developed by a task and finish group from the Council’s Internal Overview & Scrutiny Committee.

2. REPORT

Following the adoption of the Social Value Policy a few amendments need to be made to the Council’s Contract Procedure Rules to align the two documents. The Contract Procedure Rules also need to be updated to align with the Financial Procedure Rules regarding Waivers.

The following table show the suggested changes:

Sect/Para Current Wording Suggested Wording 2 – 5.1 n/a Add – ensure the Council’s Social Value Policy is complied with where applicable 5.1 Ensuring the Social Value (Public Ensuring the Social Value (Public Services) Act 2012 is complied with Services) Act 2012 is complied with for for all service contracts where the all procurements above £50k (lower if Total Value exceeds the GPA possible) Threshold; 9.4 For service contracts where the Total For all procurements over £50k (lower Value will exceed the Threshold the if possible) the Officer must give due Officer must give due consideration consideration to the Social Value to the Social Value (Public Services) (Public Services) Act 2012 prior to the Act commencement of the procurement 2012 prior to the commencement of process. the procurement process. 10 Principle: All contract awards must Principle: All contract awards must now now be made to the “most be made to the “most economically economically advantageous tender”, advantageous tender”, using a cost using a cost effectiveness approach effectiveness approach such as life- such as life-cycle costing to assess cycle costing to assess this; this may this; this may include best ‘price- include best ‘price-quality ratio’ – as quality ratio’ – as assessed on the assessed on the basis of award basis of award criteria, taking into criteria, taking into account quality and account quality considerations Social Value considerations 10.2 Selection Criteria must not include: Selection Criteria must not include: • Non-commercial Considerations; • Non-commercial Considerations unless in accordance with our Social Value Policy; 10.4 n/a Add bullet point: • Compliance with the Council’s Social Value Policy 10.5 Selection Criteria must not include: Selection Criteria must not include: • Non-commercial Considerations; • Non-commercial Considerations unless in accordance with our Social Value Policy; 16.1.4 • Social Value Act requirements • Social Value Act requirements (where applicable, i.e., for (where applicable, i.e., for all service Contracts with a Total procurements with a Total Value in Value in excess of the GPA excess of £50k); Threshold); Waivers 3.2 Where a waiver is necessary See Financial Procedure Rules 2.5 because of an unforeseeable to 2.16 on Waivers emergency involving immediate risk to persons, property or serious disruption to Council Services (Life or Death, Increased Costs/Loss of Income, Limited Markets or Reputation) the Officer must obtain the approval of the Section 151 Officer, and the Chief Executive. 3.3 The Chief Executive or the See Financial Procedure Rules 2.5 Section 151 officer may then to 2.16 on Waivers approve the waiver, but a report must be prepared for the next relevant committee to support the action taken. Where the costs exceeds £75,000 revenue or £125,000 for capital, the decision must be referred back to the Community & Resources Committee as must any decision which may have a significant effect on communities, i.e. those affecting over 2,000 residents or more than two wards.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Changes to the Contract Procedural RulesReport 176 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 14 attended
PH
Councillor Philip HackettChair, present
DB
Councillor David BrentonVice-Chair, present
JG
Councillor Jude GubbCommittee Member, present
SA
Councillor Shirleyann AndrewsCommittee Member, present
LB
Councillor Lauren BrightCommittee Member, present
SG
Councillor Stephen GibsonCommittee Member, present
GB
Gordon BryantOfficer, in attendance
SH
Steve HearseOfficer, in attendance
SD
Staci DoreyOfficer, in attendance
CS
Craig SullivanPublic, apologies
JM
Jo McCormickPublic, in attendance
BH
Brad HuttonPublic, in attendance

All 14 on the meeting page

On this subject at Torridge

Search all
  1. Changes to the Contract Procedural RulesThis decision
  2. Changes to the Contract Procedural RulesApproved

More from Torridge Audit & Governance

All decisions
MeetingDecisionOutcome
14 Jul 2026 MinutesResolved: That the minutes of the meeting held on the 31 st March 2026 be approved as a correct record. (For – 4, Aga... Approved Open
14 Jul 2026 Agreement of Agenda Items Part I and IIResolved: That the agenda as circulated be agreed. (For – Unanimous). Agreed Open
14 Jul 2026 Draft Annual Governance StatementResolved: That the draft Annual Governance Statement be approved. (Vote: For – Unanimous). Approved Open
14 Jul 2026 Whistleblowing PolicyResolved: That the revised Whistleblowing policy be approved. (Vote: For - 5, Against – 0, Abstentions – 1). Approved Open
14 Jul 2026 Annual Internal Audit ReportResolved: That the Annual Internal Audit Report be approved. (Vote: For – Unanimous). Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies