That the recommendation to update the Capital Programme with the four new projects as stated in the report be approved and recommended to Full Council. (Vote: 7, Against – 0, Abstentions – 1) That the recommendation to update the Capital Programme with the four new projects as stated in the report be approved and recommended to Full Council. (Vote: 7, Against – 0, Abstentions – 1)
Word for word from the decision Torridge published for this meeting.Source: democracy.torridge.gov.uk
Agenda Item REPORT OF Deputy Section 151 Officer To: Community & Resources Subject: Capital Programme 2025/26 to 2029/30 Date: 27th January 2025 Reference:
PURPOSE OF REPORT: For Members to consider, formulate and recommend updates to the Capital Programme 2025/26 to Full Council.
The Capital Programme includes new PIDs (Project Initiation Documents) which require authorisation from members before inclusion.
1. Introduction
1.1The Capital Programme covers the current and forthcoming five years.
It is made up of: - Approved Projects (PIDs) - New Proposed Projects (PIDs)
These are funded by: - Current Capital Reserves - Future Contributions from Revenue - Current/Future Capital Receipts - Current/Future Capital Grants
1.1Capital Programme –Updates
New PIDs
There are four new PIDs to be considered for inclusion into the capital programme (see appendix 3):
Replacement Electric Van for the Burrows 9 95 Uplift for electric vehicle
Funded from Car parks capital Parking Ticket Machines 142 85 programme, so no additional cost
Note: A minimum score of 65 is recommended for inclusion in to the capital programme. 1.2 Capital Programme – Bfwd
The brought forward balance on the Capital Programme approved by Full Council in February 2024 was:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s
Capital Programme (Feb 2024) 47,260 (50,315) (3,055)
1.3Capital Programme – Movements in the year (see appendix 1)
Movements in the year (see appendix 1) include: - Extending the programme by one year to 2029/30 - 23/24 Surplus - Operational Service Centre change to Alverdiscott road - New Projects added (Town Hall roof/Leisure works, Holsworthy Pool Decarbonisation, LAHF round 3, ACMIC Slipway etc)
Effect on Capital Programme: Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s
Capital Programme - Updated 24/25 47,825 (50,385) (2,560)
New PIDs (Yet to be approved) Funded from Sound Level Meters (Noise Monitoring Equip) 30 Surplus Audio Visual Equipment for Caddsdown 30 Surplus Burrows Electric Van (additional Cost - grant funded) 9 Surplus Parking Ticket machines (£142K) Car Park Programme
Capital Programme (2024/25) 47,894 (50,385) (2,491) 1.4 Capital Programme Split
The updated capital programme has a unallocated funds of £2.5m
However, a significant portion of this relates to the money we put aside to fund our refuse fleet in the future. (The main recycling fleet in 2025/26 and 2032/33).
Therefore, the programme can be split as follows:
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s
Vehicle Programme 4,843 (6,879) (2,035)
General Programme 43,051 (43,507) (456)
Total 47,894 (50,385) (2,491)
Note: The £2.0M surplus on the Vehicle programme is to fund the main recycling fleet replacement in 2032/33.
1.5Capital Programme – Future Pressures
The General capital programme (excluding the vehicle programme) has a surplus of £465K
Capital (Surplus)/ Funding Programme Shortfall £'000s £'000s £'000s General Programme 43,051 (43,507) (456)
However, there are significant future pressures:
- Leisure (3 centres, estimates of £60K per site per year) - Transition to Net Zero - New PIDs from 2025 to 2030 - Linear defence - working with environment agency - Future INFLATION !!!!
1.6Capital Programme – Updated
See Appendix 2 for the current capital programme by project for 2025/26 to 2029/30 Implications
Legal Implications The Council is required to set a balanced annual budget.
Financial Implications If the recommendations below are used to update the Capital Programme, then the impact on the Capital Programme is contained within this report.
Human Resources Implications There are no specific human resources implications.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Harbour Masters Quarterly ReportIt was agreed that future reports would state the quarterly period. When asked the Director of Communities & Place ad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.