Resolved
That the report be taken to Full Council for debate, with an amendment to the recommendations, removing recommendation 1. (Vote: For 6, 2 Against)
AI summaryExternal Overview & Scrutiny sends the Bideford rail report to Full Council but removes the recommendation that reinstating a railway to Bideford is unrealistic. The remaining recommendations push for coach, active travel and local links instead.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
That the report be taken to Full Council for debate, with an amendment to the recommendations, removing recommendation 1. (Vote: For 6, 2 Against)
Committee Report REPORT OF Councillor Huw Thomas – Chair of External Overview and Scrutiny To: External Overview and Scrutiny Subject: Railway Future Limited Date: 3rd June 2026 Reference:
PURPOSE OF REPORT: To discuss the recent presentation to External Overview and Scrutiny by Roger Blake of Railfuture Limit and to recommend how this impacts on Torridge and on the need to improve the connectivity of our district
1. INTRODUCTION
On Wednesday 1st April, this committee received a presentation on the Preliminary Strategic Business Case (PSBC) published by Railfuture Ltd outlining proposals to extend the current Exeter-Barnstaple railway line to Bideford..
This 132-page work, which was published in February 2026, was part-funded with £10,000 allocated by TDC in January 2024 from UK Shared Prosperity Funding. An accompanying Engineering Feasibility Study (EFS), also commissioned by Railfuture, was also published.
2. REPORT
Roger Blake, who presented the report on the PSBC, is the national infrastructure & networks director for Railfuture Ltd. He is also a founder member of the North Devon Railway Development Alliance (NDRDA) and its acting convenor.
NDRDA also lobbies for improvements to the existing Tarka Line from Exeter to Barnstaple, which is widely supported by many organisations in northern Devon, including TDC.
It should be noted that while TDC is a member of NDRDA, this does not mean that the council has previously taken a formal position on the line being extended, rather that TDC supported the PSBC studies being carried out in order to ascertain whether the project was feasible and desirable.
In his presentation, [name removed] referenced Network Rail's 2024 study, which ranked Bideford second for "strategic fit" out of 23 stations on the Western Route, indicating high potential.
Preliminary Strategic Business Case (PSBC)
The executive summary of the PSBC sets out Railfuture's justifications for the new railway service. These include: • Rail services from Bideford would help solve 'very weak socio-economic conditions and transport periphality in Northern Devon', as well as boosting regional growth and sustainable transport and tourism • Strong growth in passenger numbers on the existing Exeter-Barnstaple line and elsewhere in the SW give confidence in rail investment • The extended railway would offer a 15-minute journey time from Bideford to Barnstaple and 86 minute to Exeter Central • An expected level of usage of Bideford station of around 343,000 one-way trips per annum - or
[1] 527 daily return tickets per day (rising to 851 by 2040).
The PSBC also recognises some potential risks and other variables: • The railway extension is dependent on the existing Exeter-Barnstaple line being upgraded first. (There is no current plan or timetable for this). • The economic case for the extension is 'highly sensitive to scheme costs', as well as on improvements to the existing Tarka Line and 'assumptions on housing development' • Capital costs could be in an 'envelope' between £305m and £539m, with a mid-range cost of £422m • Some assumptions produce a Benefit Cost Ratio (BCR) of 2.0, which would represent a good investment. Other calculations produce a BCR of just 0.23 - which would be classified by the Department of Transport as 'poor' value for money
The PSBC looked at alternative routes for extending the railway back to Bideford but concluded that using the route of the old railway was the best and most cost-effective option.
Benefits
Extending the railway to Bideford would undoubtedly improve access to work, health, education and leisure opportunities for those who do not have access to their own vehicle and have to travel to Exeter and beyond in order to meet these needs.
It is possible that improved rail connections may also bring more visitors to Torridge and that this may benefit the local tourism industry.
Improved public transport would reduce pressure on existing roads and lessen congestion at peak times.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Chair's Report: Proposed Extension of Rail Services to BidefordReport | 295 KB | DownloadRead as text |
Follow External Overview & Scrutiny at Torridge and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Jul 2026 | MinutesThat the minutes of the meeting held on 03 June 2026 be agreed and signed as a correct record, with the above amendme... | Agreed | Open |
| 3 Jun 2026 | MinutesThat the minutes of the meeting held on 01 April 2026 be confirmed and signed as a correct record. (Vote: 3 For and 4... | Decided | Open |
| 1 Apr 2026 | MinutesThat the minutes of the meeting held on Wednesday 25 February 2026 be agreed and signed as a correct record. (Vote: 6... | Agreed | Open |
| 1 Apr 2026 | Consideration Of The Forward PlanIt was agreed by Members that RLNI and Coastguard would also be contacted regarding the 2026-27 meeting cycle. Counci... | Agreed | Open |
| 25 Feb 2026 | Apologies For AbsenceThat Councillor Hodson Chair the Committee in the Chair’s absence. Apologies for absence were received from Councillo... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.