Item6.3
Resolved
DECISION: 1. Agree the LCF Programme Management arrangements including delegated authority to undertake appropriate actions in respect of all matters relating to the fund including but not exclusively in respect of Premises, Debtors, Projects and performance prior to payment 2. Note the performance of the Local Community Fund programme as set out in 3.3 to 3.8 for Oct 19 – Mar 20 and the impact of Covid-19 in 3.9 and Appendix 4.1 – 4.5. 3. Agree the premises condition dispensation continues for Age UK and REAL as set out in 3.8 with future decisions made by delegated authority as part of the proposed LCF Programme Management arrangements. 4. Agree that the Infrastructure & Capacity Building funding due to Tower Hamlets Community Transport be re-purposed to fund work on restructuring options