RESOLVED – (1) That the findings and lessons learned, together with the resultant savings be noted and that in future the potential risk in respect of the child protection telephone line be regarded as a priority. (2) That the Committee joins with the Corporate Management Team in thanking those staff that continued to work over the Christmas period to maintain essential services. (3) That the Committee notes the proposed Christmas Closure in 2013 and that processes will be reviewed in light of the move back to the Town Hall and the rationalisation of some of the Council’s buildings.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This paper provides the results of a review of the Christmas closure of key administrative buildings over the period Monday 24th December 2012 to Tuesday 1st January 2013 inclusive.
Recommendation(s)
• That Employment Committee notes the findings and lessons learned, together with the resultant savings.
Contact person for access to background papers and further information:
Name: Lisa Hooley / Kate Sturman Extension: 4670 / 4326
Background Information
Relationship to Policy Aligns with the Council’s Corporate Priority of Framework/Corporate Priorities ‘Value for Money and Low Council Tax’, together with ‘Improving Health and Wellbeing of Residents’, as approximately 70% of our employees are residents of Trafford. In addition, this scheme aligns with the Council’s mission to make Trafford ‘...a great place to live, learn, work and relax’.
Financial Whilst not the primary driver, the closure of the 3 main administrative buildings for the identified period is estimated to realise savings of c£2,700 through lower usage of utilities. There will also be
1 a level of savings through reduced usage of agency staff.
Legal Implications: None
Equality/Diversity Implications In line with relevant legislation and good practice. Whilst the closure was over the Christmas period, this decision was based on service need only.
Sustainability Implications None
Staffing/E-Government/Asset Alternative arrangements were put in place to Management Implications ensure that critical services continued to be delivered during the building closure period.
Risk Management Implications As above.
Health and Safety Implications None
1. Introduction and Background
A decision was taken to close a number of the Council’s main administrative buildings (Bowfell, Quay West, Sale Waterside and Friars Court) from Monday 24th December 2012 to Tuesday 1st January 2013 inclusive. This was reached following consultations with employees via a survey and the decision was supported by the Council’s recognised Trade Unions and agreed at Employment Committee in July 2012.
It was also agreed that staff operating out of other buildings would be reduced to a minimum necessary to maintain essential services and it was estimated that the planned closures would generate savings in the region of £3,000 due to the reduced usage of gas, electricity and water.
As contingency plans were put in place, it became apparent that the closure of Bowfell would cause operational difficulties as the building was also occupied by a partner organisation requiring access to specific software that could not be accessed elsewhere. The potential savings attributed to the closure of Bowfell were minimal (c£90) and it was subsequently agreed that the building would remain open so as not to disrupt the service and to maintain relations with our partner organisation.
The Christmas Closure plans were communicated to employees via various channels and detailed that 27th and 28th December 2012 would be designated as extra-statutory days for which annual leave should be used, with staff being required to take Mondays 24th and 31st December as annual leave, flexi-time or unpaid leave. Employees were asked to have a discussion with their managers about whether they would be required to work and if not, to agree how they would take the days off and to complete the appropriate booking arrangements.
2 This paper details the feedback received following a review of the Christmas closure arrangements.
2. Feedback from Services
Feedback has been obtained from services, in order to understand whether any issues arose, so that we can learn from these in the event that consideration is given to future closures over this period. The key points – both positive feedback and areas for development - are as follows:
2.1CWB
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.