Resolved
That the content of the report be noted.
Executive noted this item on Monday 4 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the content of the report be noted.
This report provides • An update on Transformation Team activity across 2012/13 • A financial summary of all initiatives being monitored by the Board • Information about the Transformation Programme for 2013/14.
100% of all Transformation savings have now been achieved. Overall the forecast is that the savings will be £7.230m, which is £0.014m over budget.
Recommendation(s)
The report be noted.
Contact person for access to background papers and further information: Name: Sarah Maynard Extension: x1222
Relationship to Policy The successful delivery of the Transformation Framework/Corporate Priorities programme and savings will positively impact on the delivery of the corporate priorities. Financial This report presents the latest position on the Transformation savings and wider MTFP savings for 2012/13 Legal Implications: Not applicable Equality/Diversity Implications Not applicable Sustainability Implications Not applicable Staffing/E-Government/Asset This report outlines the current position of the Management Implications Transformation Team’s capacity Risk Management Implications This report outlines the transformation programme for 2013/14 and how the remaining capacity in Transformation Team will be utilised to deliver this. Health and Safety Implications Not applicable 1. Update on Transformation Team activity across 2012/13
i. The total Transformation savings realised up to the end of 2012/13 have been wide-ranging and amount to over £20m, many of which have been supported by Transformation Team:
• SWiTch (£2m cost avoidance across the 3 councils), • CCTV installation at GMP (£67k) • Finance review (£500k, over 2010-13); training review (£160k); libraries (£231k) • Welfare Reforms: Council Tax, & Social Fund (£1.4m reduced budget pressure) • Long term accommodation (£5m)
ii. In addition, the team has also been supporting the delivery of savings for 2013 – 2015, for example:
• Council wide service reviews: Revenues and Benefits (£50k); Enforcement (£62k); Information & Advice (£250k); CYPS/CWB Integration (£240k) • Stockport (£15k), NHS Integration (£300k), Libraries (£173k) • LGG mutualisation (£112k)
iii. The value added and outcomes of benefit to the council facilitated by the Transformation team include:
• Increased, specialist capacity to deliver the programme, at a time of risk to service quality & delivery • Increased internal capabilities and capacity • Robust programme governance yielding benefits realisation ahead of schedule for 2011/12 & 2012/13 • Objective challenge and support to push innovative thinking • Team costs delivered through project savings • Skills & culture transfer • Senior managers now see transformation activity as an integral part of their business as usual, enabling the Transformation Team skill set to be exploited to deliver the Councils Vision for 2015 • Council project management methodology & lifecycle • Visibility and accountability of programme in its entirety to internal and external stakeholders; thereby reducing duplication, managed interdependencies and collaboration opportunities maximised.
iv. As stated, the Transformation Team has supported the monitoring/delivery of over £20m in recurring savings since 2010, at a cost of c.£1.1m/year; expressed on a cumulative basis the total savings are £44m whilst the cost of the team has been £3.3m over the same period. Funding from the earmarked reserve, which was set up in 2009 for Transformation, has only been drawn on this year to help fund the team. 2. Financial summary of all initiatives being monitored by the Transformation Board
v. The total 2012/13 savings target is £12.161m being split between Transformation, £7.216m, and ‘other business changes’ (OBC) £4.945m.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
TRANSFORMATION PROGRAMME BENEFITS REALISATION 2012/13: PROGRESS UPDATEReport | 70 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.