Resolved
RESOLVED – (A) That the application will propose a satisfactory form of development for the site upon the completion of an appropriate Legal Agreement and that such Legal Agreement be entered into to secure a maximum financial contribution of £40,138.60 split between, £38,948.60 towards Spatial Green Infrastructure, Sports and Recreation and £1,190 towards Highway and Active Travel infrastructure. (B) In the circumstances where the Section 106 Agreement has not been completed within 3 months of this resolution the final determination of the application shall be delegated to the Chief Planning Officer. (C) That upon the completion of the above Legal Agreement, planning permission be granted subject to the conditions now determined with the removal of the condition restricting the size of delivery vehicles.
Word for word from the decision Trafford published for this meeting.
Source: democratic.trafford.gov.uk