WOODSEND CIRCLE REDEVELOPMENT - PROGRESS UPDATE

Approved Executive 1 paper

Executive approved this item on Monday 24 June 2013. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

a) That the appointment be confirmed of LSP Developments as preferred developer for the redevelopment of Woodsend Circle. b) That approval be given that all the land within the black edging on the attached plan be appropriated to Section 227 of the Town & Country Planning Act 1990. c) That the Corporate Director of Economic Growth and Prosperity be authorised to proceed with securing vacant possession of units at Woodsend Circle to facilitate the re-development of the site in accordance with the strategy set out in the report in Part II of the agenda. d) That the Acting Director of Legal Services be authorised to enter into all necessary legal agreements to support the development and transfer of the land. e) That approval be given in principle that the Council proceed to make a Compulsory Purchase Order, if required to facilitate the re-development, subject to full indemnity of costs by LSP Developments. f) That approval be given that payment for the sale of the land from LSP Developments Ltd is deferred until completion of the first phase of the development in view of the proposed strategy for securing vacant possession.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

The report; a) Summarises the current position with negotiations with LSP Developments Ltd (LSP) regarding the proposed re-development of Woodsend Circle; b) Sets out the next steps and critical actions to enable the development to proceed.

Recommendation(s)

That the Executive:

a) Confirm the appointment of LSP Developments as preferred developer for the redevelopment of Woodsend Circle. b) Approve that all the land within the black edging on the attached plan be appropriated to Section 227 of the Town & Country Planning Act 1990. c) Authorise the Corporate Director of Economic Growth and Prosperity to proceed with securing vacant possession of units at Woodsend Circle to facilitate the re-development of the site in accordance with the strategy set out in the report in Part ii of this agenda; d) Authorise the Acting Director of Legal Services to enter into all necessary legal agreements to support the development and transfer of the land. e) Approve in principle that the Council proceed to make a Compulsory Purchase Order, if required to facilitate the re-development, subject to full indemnity of costs by LSP Developments; f) Approve that payment for the sale of the land from LSP Developments Ltd is deferred until completion of the first phase of the development in view of the proposed strategy for securing vacant possession.

Contact person for access to background papers and further information:

Name: Mike Wealleans (Principal Estates Surveyor) Extension: 4491 Name: Richard Roe (Housing strategy Manager) Extension: 4265

Background Papers: None 1 Implications:

Relationship to Policy This report relates to the Corporate priority Framework/Corporate Priorities economic growth and development.

Financial The cost of vacant possession will be the responsibility of the developer once the arrangement has gone unconditional but until that time the responsibility lies with the Council. In the event the Council is required to finance any costs in advance of this date these will ultimately be treated as a cost of development and be reimbursed by the developer.

This development will have a positive impact on the business rates and council tax taxbase.

Legal Implications: Due process has been followed in relation to the proposed sale of the land and will be effected through the completion of formal agreements/transfer. The various legal agreements will also need to reflect the position in relation to both the costs of securing vacant possession in order to ensure that the costs will be payable by the developer once the agreement has become unconditional and also the deferral of the capital receipt.

Equality/Diversity Implications None Sustainability Implications The proposed development will provide a scheme that is sustainable and has minimal environmental impact. Staffing/E-Government/Asset The recommendations will assist Asset Management Implications Management in achieving the disposal of this asset as part the Land Sales Programme for 2013/2014. Risk Management Implications The Agreement with LSP Developments Ltd will contain a frequently reviewed Risk Schedule to cover the whole development. The Experian Credit Check for 2012 states that LSP Developments Ltd are scored ‘B Limited Risk (normal)’ Public Health Implications None. Health and Safety Implications None.

Background

1.1Woodsend Circle is a 1960s, predominately three-storey, block comprising nine retail units and a doctor’s surgery on the ground floor, with 11 maisonettes above. Six of the retail units are holding over under expired leases, and the other three are currently vacant. The doctor’s surgery is on an annual tenancy, and is due to relocate to a unit within the Trafford General site by December 2014 at the latest. Nine of the residential units are managed by

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
WOODSEND CIRCLE REDEVELOPMENT: PROGRESS UPDATEReport 476 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 36 attended
MC
Councillor Matthew ColledgeChair, present
SA
Councillor Sean AnsteeVice-Chair, apologies
DK
Councillor Dr. Karen BarclayCommittee Member, present
ML
Councillor Miss Linda BlackburnCommittee Member, present
MC
Councillor Michael CornesCommittee Member, present
JC
Councillor Jonathan CoupeCommittee Member, present
MH
Councillor Michael Hyman J.P.Committee Member, present
AM
Councillor Alan MitchellCommittee Member, present
AW
Councillor Alex WilliamsCommittee Member, apologies
MY
Councillor Michael YoungCommittee Member, apologies
DA
Councillor David ActonGuest, in attendance
SA
Councillor Stephen AdsheadGuest, in attendance

All 36 on the meeting page

On this subject at Trafford

Search all
  1. WOODSEND CIRCLE REDEVELOPMENT - PROGRESS UPDATEThis decision
  2. Application for planning permission 81926/full/2013 - lsp developments ltd - woodsend circle, urmstonAgreed
  3. Proposed stopping up of highway at woodsend circle, flixton m41 8gyDecided

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies