Resolved
That the latest forecast and planned actions be noted and agreed.
Executive noted this item on Monday 28 October 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
That the latest forecast and planned actions be noted and agreed.
The approved revenue budget for the year is £159.003m. The forecast for the end of the year, as projected following five months of activity, is £158.416m being a net underspend of £(0.6)m, (0.4)% of the budget. In addition, the Learning Disability Recovery plan is forecasted to achieve £(0.6)m of in-year cash savings. The main areas of budget variance are summarised as:
Forecast Movement Activity £m £m Vacancy management & control (0.6) (0.2) Social Services demand led budgets 1.2 0.7 Projects/savings rescheduling 0.2 - Running costs 0.4 - New Grant (0.2) - Income (0.2) - Service Outturn 0.8 0.5 Additional Airport dividend (1.3) - Other Council-wide savings (0.1) - Forecasted outturn (0.6) 0.5
Learning Disability Pool (0.6) (0.1)
Reserves The forecast level of General Reserve at year end is £(10.3)m. After taking into account future planned commitments the long term balance is £(8.2)m, £(2.2)m above the minimum level of £(6.0)m. The net service carry forward reserves at the beginning of the year were £(3.6)m. With a planned use to support savings and change projects of £2.3m, plus a net overspend of £0.8m, the projected carry forward is £(0.5)m. The Learning Disability Pool reserve had an adverse brought forward balance of £1.5m, which will be reduced by the recovery plan in-year to £0.9m, with a view to full recover by the end of next year. Council Tax There is an in-year forecasted Council Tax surplus, of £(0.609)m, an improvement of £(0.051)m since last period largely due to a reduction in the amount of Council Tax Support being awarded.
1 Business Rates It is too early to tell from the data available what the end of year position will be, and work continues to obtain clarity. Welfare Reform Trafford Assist and other welfare support schemes have been successfully implemented operationally and after five months are managing within planned financial limits.
Recommendation(s)
It is recommended that: a) the latest forecast and planned actions be noted and agreed.
Contact person for access to background papers and further information:
Head of Financial Management Extension: 4302
Background Papers: None
Relationship to Policy Value for Money Framework/Corporate Priorities
Financial Revenue expenditure to be been contained within available resources in 2013/14. Legal Implications: None arising out of this report Equality/Diversity Implications None arising out of this report Sustainability Implications None arising out of this report Staffing/E-Government/Asset Not applicable Management Implications Risk Management Implications Not applicable
Health and Safety Implications Not applicable
Director of Finance:CCCCCCCCCCID
Director of Legal & Democratic Services:CCCCMRJ
Signature: [Appended in hard copy.]
2 Budget Monitoring - Financial Results
1. The approved budget is £159.003m. Based on the budget monitoring for the first 5 months of the year, the overall forecast for the year is £158.416m, being an underspend of £(0.587)m, (0.4)%. Included within this total is a net service overspend of £0.777m or 0.6% of the relevant budget, and underspends in Council-Wide budgets of £(1.364)m or (5.7)% of the relevant budget.
2. The Learning Disability (LD) Pool recovery plan is forecasted to achieve £(0.597)m or (0.7)% of cash savings to offset the brought forward adverse balance on the fund of £1.472m. The details of service variances can be found in Annexes 1 to 4, and for Council-Wide, Annex 5:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
REVENUE BUDGET MONITORING 2013/14: PERIOD 5 (APRIL: AUGUST 2013)Report | 409 KB | DownloadRead as text |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.