(1) That the content of the report and progress made to date be noted and welcomed. (2) That a copy of the covering letter that will accompany the Rent Grant Questionnaire be given to Members. (3) That a copy of the schedule of all assets held by the Council be made available to Members. (4) That a revised updated list of community assets be made available to Members.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The report summarises the approach to implementation set out in the previous report to the Scrutiny Topic Group and the report approved at Executive on the 24th June 2013.
Recommendation(s)
To note the contents of this report and progress made to date.
Contact person for access to background papers and further information:
Name: Andy Prideaux, Head of Property and Development Extension: 4264
Attachments:
Appendix i Rent Grant Questionnaire Appendix ii Update list of Council property assets Appendix iii Revised Community Right to Bid procedure
Background
1.1Following the Scrutiny Topic Group meeting on 16th May 2013, the draft Community Asset Report was approved at the Executive meeting on 24th June 2013. Since then Officers have been implementing the agreed proposals and progress to date is detailed below.The programme of work is now in the implementation stage and the first tranche of agreements are progressing well.
2.0Rent Grant Review 2.1 All Rent Grants (26 in total) awarded by the Council have been identified, and a questionnaire (copy attached) is currently being sent to groups / organisations currently receiving a rent grant. Groups will be asked to respond promptly to the questionnaire and it is proposed that 4 weeks should be sufficient for this. Once all questionnaires are returned, a summary will be prepared with recommendations regarding the future of rent grant awards to organisations.
3.0Staff Resourcing
3.1A recommendation made by the Scrutiny Topic Group concerned consideration of the necessary staff resourcing required to carry out negotiations for regularising property agreements, and whether there were sufficient resources in place to carry out the review.
3.2Resourcing arrangements for the Asset Strategy are currently being reviewed and if necessary a business case will be put together regarding the possible employment of additional staff on fixed term contracts to assist with regularising the property agreements. Once the negotiations and the relevant documentation is completed, less officer time will be needed to oversee these properties.
3.3The project plan indicated that the programme should be completed by the end of March 2015 and this is still the intention.
4.0Exceptions policy
4.1Whilst it is the intention that Voluntary and Community groups will accept responsibility for the running and maintenance costs of the buildings they occupy, it is accepted that there will be groups who will not be able to enter into such agreements.
4.2Each case is being looked at individually, and where appropriate and subject to approval, exceptions may be made whereby the Council retain liability for repairs or other associated costs. This would be subject to the occupier making a contribution based on their ability to fund. Other options such as “tapering” the costs of repairs over several years will also be considered.
5.0Regularising voluntary and community sector agreements
5.1An updated list of property assets occupied by sports clubs, community and voluntary organisations, allotments societies and charities is attached to this report.
5.2The indicative timescales for consideration of transfers/regularising agreements in the original Council Asset Strategy report suggested that buildings where agreements are in place, but the occupants are holding over, would be prioritised. However, after further review of the risks and issues, officers recommend that negotiations should be prioritised for buildings that incur considerable running costs (maintenance / repairs / rates and utility costs) in order to minimise budget pressures. The properties highlighted with a 1 in appendix (ii) will be prioritised first.
5.3Where more than one group is based in a property, the occupiers have been listed and split to highlight the number of agreements that need to be reviewed / negotiated.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.