Item58
Resolved
RESOLVED – (A) That the application will propose a satisfactory form of development for the site upon the completion of a Deed of Variation in relation to the Legal Agreement that formed part of the original planning permission 76204/FULL/2010 to secure a maximum financial contribution of £148,905 split between: £43,497.00 towards Public Transport, £21,708.00 towards Highway Infrastructure, £83,700.00 towards Red Rose Forest (to be reduced by £310 per tree planted on site in accordance with an approved landscaping scheme). (B) That upon the completion of the above Deed of Variation, planning permission be granted subject to the conditions now determined.
Word for word from the decision Trafford published for this meeting.
Source: democratic.trafford.gov.uk