That the proposals in relation to the Environmental Enforcement Service be approved as set out in the report subject to the there being no significant issues arising out of the further formal consultation detailed in Para. 5.13 of the report. In particular the Executive agrees to: · the disestablishment of the Environmental Enforcement Team; · the retention of two posts for a period of 12 months to manage the transition to the proposed new way of working; · a further review of the service after 12 months; the proposals for partnership working and community engagement as set out in the report and as will be further defined in the proposed Environmental Strategy.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
A report was approved by Executive on 24th June 2013, recommending the disestablishment of the Environmental Enforcement Team. The role and function of the Team was considered as part of the Council’s on-going budget review process and it was determined in the context of that process that this service was too costly to deliver if it was not capable of being self-funding.
That decision was subjected to call in and was considered by a Scrutiny Topic Group. Following extensive engagement with Scrutiny Members the proposals have been amended as a result of their comments and now include provision for the retention of an additional 1 FTE post to work alongside the retained manager to assist and support during the transition period.
The new approach will ultimately see up to 100 frontline staff and partners being the eyes and ears of the Council, empowered to challenge anti-social behaviour that is harmful to the environment. Additionally, CCTV cameras will be used to gather intelligence to inform the new approach to change the behaviour of Trafford residents. Education and publicity, combined with the involvement of Trafford’s Locality Partnerships, will be key elements in promoting wider environmental awareness and responsibility. A number of staff are to be trained to issue FPN’s; these will be issued where challenge and education fails to bring about a change in behaviour.
This report seeks the approval of the Executive to proceed with the implementation of the proposals so that some budget savings can be delivered as planned in 2013-14; as a result of this further review not all of the planned savings are now achievable .
Recommendation(s)
That the Executive approve the proposals in relation to the Environmental Enforcement Service as set out in the report subject to the there being no significant issues arising out of the further formal consultation detailed in Para. 5.13 of the report. In particular the Executive agrees to:
1 • the disestablishment of the Environmental Enforcement Team;
• the retention of two posts for a period of 12 months to manage the transition to the proposed new way of working;
• a further review of the service after 12 months;
• the proposals for partnership working and community engagement as set out in the report and as will be further defined in the proposed Environmental Strategy.
Contact person for access to background papers and further information:
Name: Iain Veitch Extension: 4174
Background Papers: None
2 Relationship to Policy Low Council Tax and Value For Money Framework/Corporate Priorities
Financial The amendment to the original proposals following Scrutiny call in will reduce the final delivery of the agreed budget savings, and savings for 2013/14 have not been realised due to the delays in agreeing a way forward.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.