IMPLEMENTATION OF THE TRAFFORD COMMUNITY INFRASTRUCTURE LEVY
AgreedPlanning1 paper
Planning Development Control Committee agreed this item on Thursday 5 June 2014. Below is the council's own wording, with the papers it was decided on.
That Members note · the forthcoming changes to the planning process due to the implementation of CIL · that those planning applications that are “minded to grant subject to a section 106 agreement” but are not signed prior to 7 th July 2014 will need to be reconsidered by the Planning Committee.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report is to inform Planning Development Control Committee about the implementation of the Community Infrastructure Levy on 07 July 2014.
Recommendation
That Members of Planning and Development Control Committee: • Note the forthcoming changes to the planning process due to the implementation of CIL. • Note that those planning applications that are “minded to grant subject to a section 106 agreement” but are not signed prior to 07 July 2014 will need to be reconsidered by planning committee.
Contact person for access to background papers and further information:
Name: David Pearson / Melanie Craven Extension: 3198 / 1484
Background
1.1The Community Infrastructure Levy (CIL) was created under the terms of the Planning Act 2008, and established a new system for collecting developer contributions to fund essential infrastructure.
1.2Trafford Council has been developing a Charging Schedule to deliver a CIL for the Borough. At its meeting on 26 March 2014, Full Council formally approved the Trafford CIL Charging Schedule and supporting documents for implementation on Monday 07 July 2014. Changes to the validation checklist to allow for the introduction of CIL were also considered by Planning & Development Control Committee in April 2014.
1.3Planning permissions issued on or after 07 July 2014 will be determined under CIL, therefore the Planning Committee held on 05 June 2014 will be the final meeting of the committee prior to the introduction of CIL.
1 2.0 Implications
2.1Upon its introduction, CIL will replace many of the developer contributions currently required by the Council’s Supplementary Planning Document 1 (SPD1): Planning Obligations (February 2012). To ensure that developments do not pay twice for the same type of infrastructure, SPD1 has been revised to scale back contributions secured through the use of legal agreements. SPD1 2014 will be used for development management purposes to assist in the implementation of CIL from.
2.2The types of infrastructure that CIL monies can be spent on must be listed in a formal document known as the “Regulation 123 list”. This document has been approved for use, and will be subject to further consultation in advance of April 2015, when it is anticipated that developments that are CIL liable will start to be developed. An extract of the infrastructure projects that could benefit from the application of CIL monies is provided in Appendix 1 of this report.
2.3Planning applications that are subject to a legal agreement should be signed and the decision notice issued prior to the introduction of CIL. If the legal agreement is not completed before 07 July 2014, the application will then fall under the CIL regime, and may potentially incur a CIL liability instead. After this date the Council will not lawfully be able to request a S106 agreement for infrastructure provision that is the same as that which CIL will fund. As of 20 May 2014, there were 51 unsigned legal agreements still being worked upon.
2.4In line with the Trafford Charging Schedule, the following types of development that will generally incur a CIL liability are as follows: • New houses across the borough • Apartments in the south of the borough • Supermarkets outside of town centres • Retail units for bulky goods • Leisure uses and hotels
2.5It should be noted that in Trafford the following types of development will not generate a CIL liability: industry and warehousing, offices, affordable houses, apartments in the “cold” and “moderate” charging zones and public/institutional facilities.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.