CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Trafford Metropolitan Borough Council
STAR Joint Committee, Wednesday 1 October 2014 at 6.00pm

NEW EUROPEAN PROCUREMENT LEGISLATION

Noted Committee 1 paper

STAR Joint Committee noted this item on Wednesday 1 October 2014. Below is the council's own wording, with the papers it was decided on.

Item4b

Resolved

That the report be noted.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to STAR Joint Committee

Item 5b.

New European Procurement Legislation – Summary of current understanding

1. Introduction:

1.1The new EU Procurement Directives were formally approved by the EU in April 2014. The UK is still in the process of transposing these into UK law/regulations but despite stating that it intends to implement them before the end of 2014, it is more likely to be early 2015. This is in advance of the 2 year implementation period within the Directives.

1.2These notes are a high level summary and interpretation of the new EU Procurement Directives at this time but may change depending on what is transposed into UK Law.

2. Changes and implications: New Utilities Directive:

2.1Whilst most if not all Utilities in the UK are now private sector organisations their procurement is still highly regulated under the EU Procurement Directives. The changes are very similar to those applicable to the public sector and have imposed more regulation on the Utilities sector to bring it very much more closely aligned with the Public sector regime.

3. Changes and implications: New Concessions Directive:

3.1This is a totally new Directive covering both the Public sector and Utilities sector. A ‘Concession’ is the offer of a licence to operate a specific activity, it does not involve payment for the service but could include an income stream for the public sector organisation. Examples would be a licence to operate a café in a council owned park or a licence to operate an annual cultural event in a city.

3.2Previously concessions were not covered by EU Directives but best practice guidance advised that advertising and award of such contracts should follow procurement methodology to ensure fair and equal treatment of bidders and transparency of process.

4. Changes and implications: Public Procurement Directive:

4.1Procurement Procedure timescales (General):

Note that time limits for each stage have been shortened, including for whether eProcurement systems are being used or not.

4.2When external procurement is not necessary (Article 12): The Directive incorporates two important case law outcomes - ‘Hamburg’ covers joint co-operation arrangements between Contracting Authorities (i.e. shared services), ‘Teckal’ covers In-house contracts. An example of an in-house contract would be:

1 o Contracting Authority sets up a wholly controlled Legal Services Company and transfers its own Legal Department into it so that it can bid for external work (limited to 20% of activity) o Contracting Authority then awards this company its own legal services contract

The process of defining whether external procurement applies or not is an up front strategy consideration before embarking on procurement.

4.3eProcurement (Article 22 plus others): The aim is to move to fully electronic procurement by all buying organisations.

4.4Conflict of Interest (Article 24): This new regulation incorporates current best practice in that Contacting Authorities must take appropriate measures to prevent, identify and remedy any conflicts of interest. This includes: • As a minimum there must be safeguards to ensure that staff involved do not have an interest which would then be seen to compromise impartiality and independence • Failure to remedy the conflict is grounds for exclusion.

4.5New Competitive Negotiated and Competitive Dialogue Procedures (Articles 26, 29 and 30): • More freedom for Contracting Authorities to use these new procedures especially when a contract cannot be awarded without negotiation due to the nature, complexity, risk, legal or financial situation.

4.6Innovation Partnership Procedure (Article 31): • New procedure for innovative products, services or works not available in the market. The definition of Innovation covers a wide range of areas including production, marketing, operational practices etc. • The procedure is similar to Competitive Negotiation but has specific requirements around managing R&D and IPR issues and subsequent purchase of these rights. • May negotiate until final tenders submitted.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
NEW EUROPEAN PROCUREMENT LEGISLATIONReport 50 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 3 attended
AB
Councillor Allen BrettChair, present
PM
Councillor Patrick MyersCommittee Member, present
IR
Councillor Iain RobertsVice-Chair, present

More from Trafford STAR Joint Committee

All decisions
MeetingDecisionOutcome
21 Mar 2025 Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. Agreed Open
21 Mar 2025 Procurement act 2023 implementation update1) That the report be noted. Noted Open
21 Mar 2025 Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. Agreed Open
15 Jun 2022 Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. Noted Open
15 Jun 2022 Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies