Resolved
That the content of this report be noted. 2. That the required additional capital funding of £150k be prioritised within any re-profiling of the Council’s approved capital programme in 2014/15.
Executive noted this item on Monday 27 October 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the content of this report be noted. 2. That the required additional capital funding of £150k be prioritised within any re-profiling of the Council’s approved capital programme in 2014/15.
This report provides an on overview of the Environment and Operations services within the Economic Growth, Environment and Infrastructure Directorate, following a review undertaken by the Corporate Director and her Senior Management Team and Executive Member. It also provides a comprehensive summary for each service, setting out any changes that have taken place or are planned, what’s working well, proposed modifications and commitments to improve customer satisfaction.
The report also sets out proposals for investment and a delivery plan with timescales.
Recommendation(s)
1) That the contents of this report be noted. 2) That the required additional capital funding of £150k be prioritised within any re- profiling of the Council’s approved capital programme in 2014/15.
Contact person for access to background papers and further information:
Name: Helen Jones Extension: 2561
None.
1 Implications:
Relationship to Policy The work of the Directorate plays a major part in Framework/Corporate Priorities supporting and delivering the Council’s corporate priorities.
Financial The funding for the small capital schemes set out in Section 3. of this report will need to be prioritised within any re-profiling of the Council’s capital programme in 2014/15, totalling £150k. In the event resources are not available the expenditure will be financed by accelerating the 2015/16 Parks Infrastructure capital budget Scheme Ref 2631.
In addition, funding of up to £73k will be met from existing revenue budgets and balances brought forward from previous years.
Legal Implications: None.
Equality/Diversity Implications None.
Sustainability Implications The proposals set out in this report compliment the work of the Directorate in promoting sustainability.
Resource Implications e.g. Staffing The proposals include a fixed-term appointment. / ICT / Assets The recruitment will be carried out in accordance with the Council’s recruitment processes.
The post would be opened up to staff that are currently on the redeployment register and at risk of redundancy.
Risk Management Implications None.
Health and Wellbeing Implications None.
Health and Safety Implications The necessary health and safety procedures will be followed as the proposals are implemented.
2 1.0 Background
1.1There have been significant changes in the Economic Growth, Environment and Infrastructure (EGEI) Directorate over the last 18 months. The former Environment, Transport and Operations (ETO) Directorate and the former Economic Growth and Prosperity (EGP) Directorate have merged and the Corporate Director has carried out a review of the service areas with her Senior Management Team and the Executive Member for Environment and Operations.
1.2The focus of this review was to define service standards, to identify any required adjustments to operational practices to achieve better outcomes and to improve customer satisfaction.
1.3Savings of £2.254m have been delivered by the service areas during 2014/15 and further savings of £449k are on track to be delivered. The detail is set out in Section 2 of Appendix 1.
2.0Outcome of the Review
2.1The full summary of the Environmental Issues Workshop (the Summary Report) is attached as Appendix 1.
2.2The services are delivering the following outcomes:
The impact of the first phase of the ‘Be Responsible’ campaign in relation to dog fouling. Complaints have reduced by 20% from April to September compared to the same period last year (2013).
The new rota system is providing greater flexibility to respond to Street Scene issues at weekends and in the evenings.
The retention of 6 Green Flag awards for Trafford’s parks for 2014.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ENVIRONMENT & OPERATIONS PROGRESS UPDATEReport | 235 KB | DownloadRead as text |
PDF |
Envt & Operations Appendix 1Appendix | 395 KB | Download |
PDF |
Envt & Operations Appendix 2Appendix | 46 KB | Download |
Follow Executive at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Sep 2026 | Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... | Approved | Open |
| 21 Sep 2026 | Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... | Approved | Open |
| 20 Jul 2026 | Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... | Approved | Open |
| 20 Jul 2026 | Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... | Approved | Open |
| 15 Jun 2026 | Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.