SCRUTINY COMMITTEE
26 FEBRUARY 2015
PRESENT
Councillor A. Mitchell (in the Chair). M. Cordingley (Vice-Chairman), R. Bowker, D. Butt, L. Dagnall, [name removed], [name removed], J. Holden, B. Sharp and D. Western
In attendance Councillor M. Hyman Executive Member for Economic Growth and Planning Councillor John Reilly Executive Member for Environment and Operations
Also in attendance P. Forrester Democratic and Performance Services Manager C. Gaffey Democratic and Scrutiny Officer D. Geary Senior Business Change Manager C. Hindle Director of Contracts J. Le Fevre Director of Legal and Democratic Services R. Roe Director of Growth and Regulatory Services
APOLOGIES
Apologies for absence were received from Councillors K. Carter and J. Lloyd
18. MINUTES
RESOLVED: That the Minutes of the meeting held on 29 October 2014 be agreed as a correct record and signed by the Chairman.
19. DECLARATIONS OF INTEREST
No declarations of interests were made by Members.
20. PART I: RESHAPING TRAFFORD: ECONOMIC GROWTH, ENVIRONMENT AND INFRASTRUCTURE
Following the Scrutiny Committee presentation on the Joint Venture contracts at the meeting on 29 October 2014 (minutes 15 and 17), the Committee received a further report and presentation of the Director of Growth and Regulatory Services. This was to provide an update on the work undertaken to engage private sector partners for the delivery of a range of environmental, highways, professional, technical and infrastructure services.
The Director of Growth and Regulatory Services answered several questions from Members regarding the contract’s length, flexibility and robustness. Other Joint Venture examples were discussed and how the Council could learn from these, as well as what impact the contracts could have on local businesses.
RESOLVED: That the Committee thank the Director of Growth and Regulatory Services for the presentation and noted that it is intended to
1 Scrutiny Committee 26 February 2015
give further consideration to this matter (minute 22 refers) following a proposal to exclude the press and public.
21. EXCLUSION RESOLUTION (REMAINING ITEMS)
RESOLVED: That the public be excluded from this meeting during consideration of the remaining item of business because of the likelihood of disclosure of “exempt information” which falls within Paragraph 3 of schedule 12A of the Local Government Act 1972, as amended.
22. PART II: RESHAPING TRAFFORD: ECONOMIC GROWTH, ENVIRONMENT AND INFRASTRUCTURE
Further to the earlier presentation (minute 20 refers), the Committee received a report and presentation of the Director of Growth and Regulatory Services, containing information relating to the terms of the Joint Venture contracts.
The Director of Growth and Regulatory Services responded to a number of questions from the Committee concerning the commissioning and evaluation process, the arrangements for monitoring contract performance, the incentives for contractors to engage with local communities, and whether the initial objectives of awarding the contracts could be met.
The Committee discussed the comments that they would like to make to the Executive prior to their decision on the 16th March. These included concerns about the lack of incentives for contractors to engage with local communities. The Committee acknowledged that, whilst the need to engage with local communities was recognised, there needed to be clearer incentives to encourage contractors to engage with residents to develop innovative ways to improve services.
The Committee were also unclear as to whether the proposed savings were achievable. The Committee were concerned that the proposed savings target in year 1 would not be met which raised concerns that this would impact on current and future budgets.
The Committee also stated that it would welcome greater clarity about what would happen in the event of contractor failure. The Committee also asked for details of what would happen if a contractor ceased to exist.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MINUTESMinutes | 55 KB | DownloadRead as text |
Follow Scrutiny Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2025 | Membership of the committee 2025/26That the Membership of the Committee be noted. | Noted | Open |
| 14 Jul 2025 | Committee terms of reference 2025/26That the Committee Terms of Reference be noted. | Noted | Open |
| 14 Jul 2025 | MINUTESThat the Minutes of the meetings held on the 22 nd January and 12 th March 2025, be agreed as an accurate record. | Agreed | Open |
| 14 Jul 2025 | Leaders priorities 2025/26That the Leader of the Council’s priorities be noted. | Noted | Open |
| 14 Jul 2025 | Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.