TRAFFORD COUNCIL
Report to: Standards Committee Date: 24th June 2015 Report for: Decision Report of: Joanne Hyde – Acting Corporate Director for Transformation & Resources
Report Title
Harmonised Contract Procedure Rules (CPRs) For Stockport, Trafford and Rochdale.
Purpose
To confirm that the Committee is content for the harmonised CPRs, approved by CMT 21 May 2015, to be adopted by the Council, subject to any comments the Committee wish to make.
Recommendation(s)
That the Committee approves the harmonized CPRs for incorporation into the Constitution.
Contact person for access to background papers and further information:
Name: Sharon Robson – Director of Procurement (STaR) Extension: x1938
Background Papers: None
Relationship to Corporate Priorities Not applicable Financial Contained within the body of the report
Legal Implications: Contained within the body of the report
Equality/Diversity Implications Not applicable Sustainability Implications Not applicable Resource Implications e.g. Staffing Not applicable / ICT / Assets Risk Management Implications Contained within the body of the report Health & Wellbeing Implications Not applicable Health and Safety Implications Not applicable 1 1. BACKGROUND
1.1Following the establishment of STaR in which Stockport, Trafford and Rochdale came together to deliver their procurement functions jointly, each Council and STaR have been operating in accordance with their own Contract Procedure Rules (CPRs).
1.2STaR’s governance consists of a Board and a Joint Committee. The Joint Committee’s Terms of Reference included consideration of the CPRs under which it will operate for each of the Councils. In order to harmonise processes and deliver an effective and consistent procurement process it was considered essential that Stockport, Trafford and Rochdale (STaR) have a single set of Contract Procedure Rules (CPRs) for the three Councils.
1.3A CPR working group was established to lead on the harmonisation process. The group consisted of the Director of Procurement for STaR and representatives from Finance and Legal Services for each of the STaR Councils.
2. DRAFTING AND CONSULTATION PROCESS
2.1The first draft of the harmonised Contract Procedure Rules (CPRs) for consideration by STaR Councils was completed in November 2014 and a consultation process carried out in December 2014. The consultation documentation identified the key changes from the existing CPRs to those proposed; this information was specific to each Council. Workshops for key stakeholders were organised and consultation feedback was captured and summarised for review.
2.2As a result of the engagement process there was significant positive feedback regarding the proposed draft. Specific points included the following:
Much clearer layout and formatting
Straight forward and easy to understand
More comprehensive
The idea of a Procurement Handbook was well received, as was a simplified Scheme of Delegation
If required, the inclusion of a Schedule to the CPRs allowing for Authority specific rules was welcomed
The Procurement Initiation Document (PID) was seen as a useful tool to inform and commence the procurement process from the outset. A “light” version for lower value contracts would be beneficial
Further consideration of the role of Pre-Qualification Questionnaires (PQQs) and financial vetting was requested.
2 2.3 In addition there have been several questions and clarifications raised regarding key features of the proposed CPRs. Issues which are of particular note include:
The proposed move to a £25,000 threshold for open advertising of procurement opportunities and the impact in terms of additional resources on service managers and STaR.
Clarity regarding roles and responsibilities of STaR and client groups within the procurement cycle.
Requests for procurement training.
3. KEY ISSUES
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HARMONISED CONTRACT PROCEDURE RULESReport | 253 KB | DownloadRead as text |
Follow Standards Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Jun 2025 | Membership of the committee 2025/26That the membership of the Committee be noted. | Noted | Open |
| 19 Jun 2025 | Terms of reference 2025/26That the Committee Terms of Reference be noted. | Noted | Open |
| 19 Jun 2025 | MINUTESThat the Minutes of the meeting held on the 6 th March 2025, be approved as an accurate record and be signed by the C... | Approved | Open |
| 19 Jun 2025 | Agreement of work programme 2025/26That the Work Programme for the Municipal Year 2025/26 be noted. | Noted | Open |
| 19 Jun 2025 | Member developmentThat the presentation be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.