Item27
Resolved
RESOLVED – (A) That the application will propose a satisfactory development for the site upon the completion of a Legal Agreement which will secure a contribution of £44,800 towards the design and delivery of a Processional Route (as defined within Policy SL3 of the Trafford Core Strategy). (B) In the circumstances where the Section 106 agreement has not been completed within 3 months of the date of this resolution, the final determination of the application shall be delegated to the Head of Planning Services. (C) That upon the satisfactory completion of the above Legal Agreement, planning permission be granted subject to the conditions now determined.
Word for word from the decision Trafford published for this meeting.
Source: democratic.trafford.gov.uk