RESOLVED – (1) That the report be noted. (2) That the Leader of Trafford Council be advised of STaR Procurement’s objective to secure new partners and increase active involvement in Greater Manchester and asked to engage with the Combined Authority, with a means of securing an item on its agenda.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The purpose of this report is to: Provide an update on progress made to the end of Q2 on the Action Plan that supports the delivery of the STAR Business Plan 2016/17
Recommendations
The recommendation of this report is that the STAR Board: Note the progress made to the end of Q2 on the Action Plan that supports the delivery of the STAR Business Plan 2016/17
Contact person for access to background papers and further information:
Name: Nichola Cooke Phone: [phone removed]
Background
Financial Impact: None Legal Impact: None Human Resources Impact: None Asset Management Impact: None E-Government Impact: None Risk Management Impact: None Health and Safety Impact: None
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Consultation
No public consultation required
Reasons for Recommendation(s)
The STAR Business Plan 2016/17 sets out the strategic direction and priorities for procurement for the participating partners of STAR. The Action Plan is an ambitious plan to help us deliver these priorities and this report provides an update on progress to date.
Contact person for access to background papers and further information:
Name: Nichola Cooke Phone: [phone removed]
1.1The STAR Business Plan 2016/17 sets out the strategic direction and priorities for procurement for the participating partners of STAR. This is our first Business Plan for STAR Procurement and is an indication of how we are now establishing ourselves as a proactive service that is planning for the future. The Business Plan was launched in July 2016 following approval by STAR Joint Committee.
2. STAR Business Plan Action Plan Progress Report
2.1The Business Plan Action Plan is an ambitious plan as to how we are going to deliver the vision and objectives of the Business Plan 2016/17. The action plan is used by STAR SMT to monitor progress, maintain momentum and focus so that we are able to achieve the best possible results for STAR, Partner Councils, Clients and the boroughs which we serve. 2.2 Given the detailed nature of the action plan it is available to internal stakeholders only. 2.3 The action plan lists actions required, an associated implementation plan, key milestones and a lead identified. The action plan is reviewed on a quarterly basis to ensure that momentum is maintained and to ensure it remains relevant and appropriate. The Business Plan Action Plan has been used to inform the PDR process and actions are aligned to objectives for all members of STAR SMT.
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils 2.4 A Q2 review has been undertaken and the progress to date for each action is set out in the Action Plan at Appendix 1. 2.5 Progress to date has been significant with a majority of actions for Q1, 2 and 3 either complete or well underway. Priorities have been identified for Q3. 2.6 However the programme of action has been challenging, especially given the fact that the third Head of Strategic Procurement post has been vacant. In addition, the fact that that the current DoP is leaving has meant that activities associated with interim planning and the recruitment process has impacted on progress in certain areas. 2.6.1 Where targets against the specified time plan have not been achieved this is highlighted in red and additional focus will be provide in Q3 to ensure that the Business Plan objectives are achieved. 2.6.2 The actions have been led by STAR SMT but with involvement of the entire STAR team. STAR SMT has been constrained due to the vacancy at Head of Strategic Procurement but it is a real positive that the STAR Business Plan Action Plan is still being delivered alongside the day to day management responsibilities.
3 Next Steps
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.