Resolved
That the report be noted.
Accounts and Audit Committee noted this item on Wednesday 23 November 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The purpose of this report is to inform Members of the current 2016/17 forecast outturn figures relating to both Revenue and Capital budgets. It also summarises the latest forecast position for Council Tax and Business Rates within the Collection Fund.
Recommendation(s)
It is recommended that: a) the Executive note the report and the changes to the Capital Programme as detailed in paragraph 19.
Contact person for access to background papers and further information:
David Muggeridge, Finance Manager, Financial Accounting Extension: 4534
Background Papers: None
Relationship to Policy Value for Money Framework/Corporate Priorities
Financial Revenue and Capital expenditure to be contained within available resources in 2016/17. Legal Implications: None arising out of this report Equality/Diversity Implications None arising out of this report Sustainability Implications None arising out of this report Resource Implications e.g. Staffing Not applicable / ICT / Assets Risk Management Implications Not applicable
Health & Wellbeing Implications Not applicable
Health and Safety Implications Not applicable
1 Other Options
Not Applicable
Not Applicable
Not Applicable
Finance Officer Clearance NB……………… Legal Officer Clearance ………… …JLF…
CORPORATE DIRECTOR’S SIGNATURE:
2 REVENUE BUDGET
Budget Monitoring - Financial Results
1. The approved budget agreed at the 17 February 2016 Council meeting is £147.32m. In determining the budget an overall gap of £22.64m was addressed by a combination of additional resources of £6.26m, including projected growth in business rates, council tax and use of general reserve and £16.38m of service savings and additional income. 2. Based on the budget monitoring for the first six months, the year end forecast is showing a small overspend figure of £214k, the Corporate Leadership Team will be working with operational areas over the next six months with the aim of delivering a balanced budget out-turn. 3. The summary details of service variances against budget are shown in Table 1 and Table 2 below.
2016/17 Forecast Forecast Table 1: Budget Monitoring Budget Outturn Variance Percent- results by Service (£000’s) (£000’s) (£000’s) age Children’s Services 29,911 32,233 2,322 7.8% Adult Services (Inc. Public 46,652 46,910 258 0.6% Health) Economic Growth, Environment 32,198 31,919 (279) (0.9)% & Infrastructure Transformation & Resources 16,939 16,239 (700) (4.1)% Total Service Budgets 125,700 127,301 1,601 1.3% Council-wide budgets 21,620 20,233 (1,387) (6.4)% Forecast outturn (period 6) 147,320 147,534 214 0.1%
Dedicated Schools Grant 119,428 120,595 1,167 1.0% Public Health 13,334 13,414 80 0.6%
Main variances, changes to budget assumptions and key risks
4. Historically service variances at year end have been moved into service earmarked reserves and the current balances on those are detailed in Paragraph 12. A number of firm commitments already exist on those reserves largely to support transformational projects which limit the ability to absorb the full extent of the in-year pressures, particularly in CFW. It is proposed that where any in-year overspend cannot be funded from that particular service reserve then it will be met from the in-year underspend of the other directorates. If management actions are not able to reduce the current projected overspend of £214k, a balancing contribution will be required from the uncommitted CFW service earmarked reserve as detailed in paragraphs 12 & 13.
5. The significant demand led pressures being placed on the Children’s Service placement budget are being addressed in the current year predominantly through the use of one off savings within Council Wide budgets and brought forward service earmarked reserves. However, the recurrent nature of the
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BUDGET MONITORING 2016/17: PERIOD 6 (APRIL TO SEPTEMBER 2016)Report | 149 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.