That the alternative delivery strategy as detailed in the report at p.5. agenda pack p.31, under the heading “Change of strategic delivery approach”, utilising the Greater Manchester Combined Authority Compulsory Purchase powers, be approved. 2. That authority be delegated to the Chief Executive, in consultation with the Leader, to present a report to the Combined Authority requesting that a Compulsory Purchase Order is promoted by the Combined Authority in respect of the Cornbrook neighbourhood, as detailed in appendix one to the report. The report will ask the Combined Authority to appoint Manchester City Council to act on its behalf in taking all necessary steps to prepare the case for the CPO, including but not limited to securing an appropriate indemnity in respect of the Combined Authority’s costs in promoting and making the CPO.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report seeks Executive approval to utilise Combined Authority powers and to delegate authority to the Chief Executive in consultation with the Leader to present a report to the Greater Manchester Combined Authority requesting that a Compulsory Purchase Order is made in respect of the Cornbrook neighbourhood.
Recommendation(s)
The Executive will be asked to:
1. Approve the alternative delivery strategy as detailed in section 2 below, utilising the Greater Manchester Combined Authority Compulsory Purchase powers.
2. Delegate authority to the Chief Executive, in consultation with the Leader, to present a report to the Combined Authority requesting that a Compulsory Purchase Order is promoted by the Combined Authority in respect of the Cornbrook neighbourhood, as detailed in appendix one. The report will ask the Combined Authority to appoint Manchester City Council to act on its behalf in taking all necessary steps to prepare the case for the CPO, including but not limited to securing an appropriate indemnity in respect of the Combined Authority’s costs in promoting and making the CPO
Contact person for access to background papers and further information:
Name: Richard Roe Extension: 4265
Background Papers: None
1 Implications:
Relationship to Policy This report relates to the corporate priority for Framework/Corporate Priorities economic growth and development and will support the delivery of a strategic regeneration site.
The Cornbrook Hub Strategic Regeneration Framework (SRF) sets the objectives of delivering a distinctive location which will support the continued growth of the Manchester and Trafford’s economies.
The SRF will see the creation of a residential and commercial destination around a major transport hub. The delivery of this will provide a range of new employment and residential opportunities. Financial All revenue costs including officer time will be reimbursed under the terms of the agreed indemnity agreement. All capital costs will be reimbursed under the terms of the agreed indemnity agreement Legal Implications: The relevant legal process will be pursuant to the Greater Manchester Combined Authority Compulsory Purchase powers and an indemnity agreement will be entered into as referred to in the report
Equality/Diversity Implications The land subject to the SRF is included within one of the Strategic Locations in the Trafford Core Strategy. During its preparation, that document was subject to an Equalities Impact Assessment (EIA) to ensure that equality issues have been considered as part of the preparation. Sustainability Implications The Trafford Core Strategy was subject to an independent sustainability appraisal as part of its preparation. Resource Implications e.g. Staffing The preparation of the CPO will require staff / ICT / Assets resources from within the Strategic Growth Service; the Planning and Development Service and; Legal and Democratic Services, however all costs will be reimbursed under the terms of an indemnity agreement Manchester Ship Canal Developments. Risk Management Implications The project team will meet on a regular basis and review any issues, risks which may arise. A key objective of the SRF is to deliver one of the Strategic Locations in the Council’s Core Strategy. If the proposed CPO is not progressed it could undermine the delivery of this key site, which could in turn put the delivery of the Council’s overall strategy at risk.
2 Health & Wellbeing Implications No direct implications Health and Safety Implications No direct implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.