Resolved
That the report be noted.
Scrutiny Committee noted this item on Wednesday 11 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The Executive’s Draft Budget Proposals for 2017/18 were agreed at its meeting held on 15 November 2016. The Leader of the Council gave a presentation to the Scrutiny Committee on 16 November 2016 setting out the proposals.
Two Budget Scrutiny Working Group sessions were then held during December with relevant Executive Members and senior officers attending to give background to the proposals and answer questions.
This report reflects the outcome of those discussions and summarises issues for the Executive’s further consideration in developing its final proposals and response.
The Budget Scrutiny report identifies that Scrutiny Members feel that there are three key, crosscutting areas where the Executive needs to satisfy itself of the robustness of the proposals. These are:
£2m budget gap Risk assessments Ensuring that forward projections for demand led services are robust
The Scrutiny Committee have also identified a number of specific areas of the proposals where they felt more information was required on how these savings would be achieved and managed. These include:
Parking Fees School Crossing Patrols Waste Management Grounds Maintenance (Bowling Greens)
Recommendation(s)
That the Executive consider and respond to the report and recommendations made.
1 Contact person for access to background papers and further information:
Name: Chris Gaffey, Democratic and Scrutiny Officer
Extension: 2019
Background Papers: None
2 BUDGET SCRUTINY REPORT - 2017/18 Foreword by the Chairman and Vice-Chairman of Scrutiny Committee
We welcome the Executive’s decision to consult widely on its budget proposals, and the opportunity for Scrutiny Members to review and comment on them at an early stage.
Budget Scrutiny 2017/18 has once again been a challenge for, and made significant demands on, all those involved. On behalf of Scrutiny Members, we would like to thank the Executive, Corporate Leadership Team and Scrutiny Councillors for their patience and contribution to the process. We would particularly like to thank Councillor Joanne Harding for chairing one of the sessions.
Members acknowledged that the Council continues to work within an increasingly challenging financial climate and the focus of Scrutiny input has been on the robustness and deliverability of the current proposals in the light of experience of budget savings already made in previous years, and the potential impact on communities and service users.
We hope that our Budget Scrutiny will contribute to the decision making process and in ensuring that robust processes are in place to manage changes. We have identified areas where we feel that there are risks to delivery and to users and we look forward to receiving details of how the Executive will address these.
Councillors Michael Young and Mike Cordingley Chairman and Vice-Chairman, Scrutiny Committee. December 2016
3 1.0 Background
This year the approach to budget scrutiny was agreed by the Scrutiny Committee, with a programme designed to forward any recommendations / observations to the Executive at the earliest opportunity in response to its consultation.
Two Budget Scrutiny Working Group sessions were held to look at the proposals. The approach this year was to look at the proposals using the themes identified for budget consultation. Scrutiny Members noted that the approach to the budget shortfall for 2017/18 and later years has focused on a “One Council” approach by taking a cross directorate view to the savings that need to be achieved by applying the following themes:-
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BUDGET SCRUTINY REPORT TO EXECUTIVEReport | 84 KB | DownloadRead as text |
Follow Scrutiny Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2025 | Membership of the committee 2025/26That the Membership of the Committee be noted. | Noted | Open |
| 14 Jul 2025 | Committee terms of reference 2025/26That the Committee Terms of Reference be noted. | Noted | Open |
| 14 Jul 2025 | MINUTESThat the Minutes of the meetings held on the 22 nd January and 12 th March 2025, be agreed as an accurate record. | Agreed | Open |
| 14 Jul 2025 | Leaders priorities 2025/26That the Leader of the Council’s priorities be noted. | Noted | Open |
| 14 Jul 2025 | Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.