Resolved
That the report be noted.
STAR Joint Committee noted this item on Tuesday 2 May 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
The purpose of this report is to highlight to the STAR Joint Committee, the ‘stocktake’ position for STAR Procurement as at 31st March 2017
The recommendation of this report is that the Joint Committee notes the contents of the report
Contact person for access to background papers and further information:
Name: Lorraine Cox Phone: [phone removed]
Financial Impact: None Legal Impact: None Human Resources Impact: None Asset Management Impact: None E-Government Impact: None Risk Management Impact: None Health and Safety Impact: None
No public consultation required
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Reasons for Report
Since commencing as the new Director of STAR Procurement on 3rd January 2017, I felt it appropriate to undertake a ‘Stocktake’ of STAR Procurement (STAR) with my Senior Management Team, in terms of reviewing the ‘as is’ position and to celebrate the success to date. This has also enabled us to reflect on future planned activity and this has fed into the creation of the draft Business Plan 2017-2020.
1. Summary of Stocktake
1.1Success to date
Awards: STAR Procurement was highly commended for Collaboration at the GO Awards ceremony on 21st March 2017. STAR Procurement was also a finalist at the LGC Awards 8th March 2017 for ‘Team of the Year’.
Balanced Scorecard: Position for 16/17 reports, is outlined below; a full and final position will be presented to the next Joint Committee:
Compliance C1: Number of contracts in the work plan awarded without a successful legal challenge against the total number of contracts in the work plan: Target 100% – Delivered: 100% C2: % of ‘live’/ compliant contracts in the Contracts Register against the total number of contracts in the Contracts Register in year: Target: 90% – Delivered: 94% C3: % of signed contractual documents filed on The Chest for contracts over three months: Target: 90% – Delivered: 82%.
Finance STAR has exceeded the savings target for 16/17: Target: £3.6M – Delivered: £3.678M (102%) * this may improve again at financial close.
Social Value S1: Number of local employment opportunities created as defined in GMCA Social Value Policy: Target: 150 – Delivered: 303. S2: % of tender exercises resulting in Social Value KPIs: Target: 50% - Delivered: 58%.
STAR Procurement is the shared procurement service for Stockport, Trafford and Rochdale Councils Performance 87% satisfied customers
1.2Staffing
Our established staffing structure has been static for some months now with only three vacancies, two of which we have promoted procurement officers into acting up positions into the two category manager roles. The third post is the P.A. to Director of Procurement, at present we don’t feel this is required. We have two temporary agency staff supporting STAR on the Stockport Together project and Working Health project, both externally funded. Recruitment has commenced for an agency person for the Learning & Disability (LD) Tender but due to limited response from Reed Agency we will be searching with wider suppliers, this activity is also externally funded.
1.3Income Secured (2017-18)
Income secured for 17/18 £156.5K as at April 2017; this is referenced in more detail in the finance report.
1.4AGMA Collaborative Procurement
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STAR PROCUREMENT UPDATEReport | 252 KB | DownloadRead as text |
Follow STAR Joint Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2025 | Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. | Agreed | Open |
| 21 Mar 2025 | Procurement act 2023 implementation update1) That the report be noted. | Noted | Open |
| 21 Mar 2025 | Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. | Agreed | Open |
| 15 Jun 2022 | Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. | Noted | Open |
| 15 Jun 2022 | Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.