Resolved
1) That the report be noted. 2) That consideration be given to having a coordinated policy on Traffic Management and Public Health.
Scrutiny Committee noted this item on Wednesday 10 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
1) That the report be noted. 2) That consideration be given to having a coordinated policy on Traffic Management and Public Health.
This report identifies the process undertaken to consider the introduction of Pedestrian Crossings within Trafford, identifying the key stages, funding and the involvement with TfGM in introducing Signal Controlled Crossings within the Borough.
Recommendation(s)
It is recommended that the report be noted.
Contact person for access to background papers and further information:
Name: Darren Findley Extension: 2535
1 1. Introduction:
1.1This report is in response to a request by Scrutiny Committee and describes the typical processes involved when considering requests for the introduction of new pedestrian crossings in Trafford.
1.2The report covers the relationship that exists between Trafford as Highway Authority and TfGM as Highway Authority for Traffic Signals within Greater Manchester.
1.3Additionally it identifies the complex process associated with assessing the requirement for a crossing, together with an indication of typical costs.
2. Process to Establish Pedestrian Crossings:
2.1Safety is always the key issue when considering a crossing point. Crossings are provided as amenities to provide access and easier movement to pedestrians and assist them to cross the road. Generally the provision of crossings should be targeted at the needs of those people who experience most difficulty and danger.
2.2The purpose of a crossing is to provide pedestrians with passage across a carriageway. Each type of crossing has advantages and disadvantages; the type chosen should be appropriate to the circumstances of the site and the demands and behavior of road users.
2.3Guidance on the introduction of Pedestrian Crossings is provided in:
The Department for Transport Local transport Note 1/95 (see item No1 in the Appendix for a link to this document) The Assessment of Pedestrian Crossings & 2/95 The Design of Pedestrian Crossings. (see item No2 in the Appendix for a link to this document)
3. How we assess the need for a pedestrian crossing
3.1We will assess the level of need for a crossing by:-
3.2Measuring the degree of conflict between pedestrians crossing the road and the two-way traffic flow and we will also take into account the following factors
• the age and ability of pedestrians; • any suppressed demand; (the level of crossing that would occur it was easy to cross) • the different types of vehicles in the flow of traffic; • the length of time pedestrians have to wait to cross; • the width of the road; • the speed of traffic; • the pedestrian injury collision record at the site.
3.3This is a two stage process consisting initially of site observations, should they indicate further investigations a full survey is commissioned.
4. The survey
4.1If the safety requirements for a crossing can be satisfied then we will measure the degree conflict between the traffic and pedestrians by carrying out a 12-hour survey which will count both vehicles and pedestrians this is referred to as a PV2:-
• the number of pedestrians crossing in an hour (P) • the flow of vehicles in both directions in an hour (V)
2 4.2 Our assessment will be based on the average of the four busiest hours in the day (between 7am and 7pm). When the survey is carried out, the pedestrians will be classified by their age and ability. Vehicles will be classified by vehicle type so that we can take into account the differences between cars, heavy goods vehicles, buses, motorcycles and pedal cycles.
4.3We will consider the possibility that the present situation suppresses crossing demand because of the difficulty in crossing the road to access services. Where appropriate we will estimate suppressed pedestrian demand at the location and add these estimated figures to the actual measured pedestrian figures obtained by the survey.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PEDESTRIAN CROSSINGS AND TRAFFIC MANAGEMENTReport | 197 KB | DownloadRead as text |
Follow Scrutiny Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2025 | Membership of the committee 2025/26That the Membership of the Committee be noted. | Noted | Open |
| 14 Jul 2025 | Committee terms of reference 2025/26That the Committee Terms of Reference be noted. | Noted | Open |
| 14 Jul 2025 | MINUTESThat the Minutes of the meetings held on the 22 nd January and 12 th March 2025, be agreed as an accurate record. | Agreed | Open |
| 14 Jul 2025 | Leaders priorities 2025/26That the Leader of the Council’s priorities be noted. | Noted | Open |
| 14 Jul 2025 | Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.