Resolved
That the report be noted.
Scrutiny Committee noted this item on Wednesday 14 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the report be noted.
At its meeting held on 22 March 2017, Scrutiny Committee approved 4 key recommendations for improvements identified by the task and finish group subject to further consideration and approval by the Executive.
Executive considered the recommendations approved by Scrutiny Committee at its meeting held on 26 June 2017, and suggested a number of additional changes which were incorporated into development plans.
This report provides an update on progress made on the 4 key recommendations approved by the above committees.
Recommendation(s)
To note the progress made on the agreed areas for improvement as follows:- .
1. Member Communications Strategy 2. Quarterly Performance Reporting to Executive 3. Improved management arrangements to support leaf clearance programs 4. CRM Improvements
Contact person for access to background papers and further information:
Name: Melissa Wise – Director One Trafford Partnership Telephone Number: [phone removed]
1 BACKGROUND At its meeting held on 22 March 2017, the Scrutiny Committee task and finish group identified 4 key recommendations arising from a detailed review of the partnership contract with a focus on contract specifications and communications.
Scrutiny Committee then referred the recommendations to Executive at a meeting held on 26th June 2017. The Executive accepted all recommendations and noted that a further Task and Finish Group would be established to further explore the recommendation’s set out in section 4 of the report (Customer Relationship Management System) to explore the feasibility and timescales for those improvements to take place.
A further report was then provided by Scrutiny to the Executive at its meeting held on 29th January 2018 and that report should be noted in conjunction with this update.
2. PROGRESS AGAINST 4 KEY RECCOMENDATIONS
2.1Recommendation 1 – Communication Proposals
All proposals and changes requested by the Scrutiny and Executive Committees have now been incorporated and Members are now receiving a regular monthly update. Feedback from Members has been very positive and there have been no additional requests to incorporate any further content in these updates.
In addition to the monthly member update, all Members were kept informed of progress with the additional “winter clean” programme by daily updates during the period 1 December 2017 to end of January 2018 with more recent daily updates focusing on other ad hoc activity e.g. gritting programmes which have also been very well received.
A revised communication plan was introduced in November 2017 for the management of highways investment programme and was named “Keeping you Moving”. This saw the introduction of bespoke updates at a ward level for Members to ensure they were kept aware of works that were scheduled in their ward with a 1 week lead time prior to the works commencing. These updates include any changes to the originally agreed dates and these will continue to be provided until the full completion of highways investment works which is currently on track to end on 31 March 2018. Further detail of the “Keeping You Moving” Communications Strategy is attached at Appendix 1 for information.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
UPDATE ON THE TASK AND FINISH GROUP REVIEW OF THE JOINT VENTURE CONTRACT BETWEEN TRAFFORD COUNCIL AND AMEYReport | 100 KB | DownloadRead as text |
Follow Scrutiny Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2025 | Membership of the committee 2025/26That the Membership of the Committee be noted. | Noted | Open |
| 14 Jul 2025 | Committee terms of reference 2025/26That the Committee Terms of Reference be noted. | Noted | Open |
| 14 Jul 2025 | MINUTESThat the Minutes of the meetings held on the 22 nd January and 12 th March 2025, be agreed as an accurate record. | Agreed | Open |
| 14 Jul 2025 | Leaders priorities 2025/26That the Leader of the Council’s priorities be noted. | Noted | Open |
| 14 Jul 2025 | Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.