That the allocation of the approved Greenspace Capital programme as set out in the report be approved. 2. That the Corporate Director for Economic Growth, Environment and Infrastructure be authorised to make minor changes to the programme. 3. That authority be delegated to the Corporate Director, Transformation and Resources in consultation with the Chief Finance Officer to authorise the final agreed expenditure on Turn Moss following the tendering process and subject to securing planning permission. 4. That authority be delegated to the Director of Legal and Democratic Services in consultation with the Corporate Director, EGEI and where appropriate, the Chief Finance Officer to finalise and enter into all legal agreements required to implement the above decisions.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report sets out the detailed list of schemes proposed under the capital greenspace programme for 2018/19. These schemes have been identified as being of priority in the next financial year.
Recommendations
That the Executive:
1. Approve the allocation of the approved Greenspace Capital programme as set out in this report; 2. Authorise the Corporate Director for Economic Growth, Environment and Infrastructure to make minor changes to the programme; 3. Delegate authority to the Corporate Director, Transformation and Resources in consultation with the Chief Finance Officer to authorise the final agreed expenditure on Turn Moss following the tendering process and subject to securing planning permission. 4. Delegate authority to the Director of Legal and Democratic Services in consultation with the Corporate Director, EGEI and where appropriate, the Chief Finance Officer to finalise and enter into all legal agreements required to implement the above decisions.
Contact person for access to background papers and further information: Name: Melissa Wise Telephone No: [phone removed] Background Papers: None
1 Implications:
Relationship to Policy This report relates to the corporate priority for Framework/Corporate Priorities economic growth and development
Financial All capital expenditure outlined is this report is contained in the Council’s approved Capital programme for 2018/19 which was approved by Council in February 2018. Legal Implications No immediate implications as a result of the report. There will however be the need to ensure that all schemes are progressed with due regard to all relevant statutory requirements Equality/Diversity Implications No direct impllications Resource Implications e.g. Staffing No direct implications / ICT / Assets Risk Management Implications No direct implications Health & Wellbeing Implications Maintaining and enhancing a varied range of good quality play equipment and sports facilities ensures continued free access to active play for the residents of Trafford, thereby contributing to the health and well-being of our population. Health and Safety Implications The improvements proposed will improve safety for users of play equipment and sports facilities. Replacing worn play equipment and play/sports surfacing in a timely manner prevents injury to park users, in particularly children.
Background
1.1A total of £435,582 has been allocated for Greenspace projects for 2018/19 with Council funding of £200k being supplemented through the opportunity to allocate Developer contributions (S106 and Red Rose Forest monies) for a range of outdoor sports, biodiversity and parks infrastructure projects.
1.2An additional amount, up to £2.5m, has been allocated to the Leisure programme for investment in Turn Moss. This investment is subject to the Council securing planning permission for the proposed improvements and additional facilities.
2 2.0 GREENSPACE CAPITAL PROGRAMME
2.1Trafford Council and the One Trafford Partnership are responsible for the strategic management and maintenance of a greenspace resource comprising 37 public parks, 50 amenity green spaces, 21 recreation/sports grounds, five cemeteries/crematoria, 41 woodlands, 86 children’s playgrounds and 36 allotment sites.
2.2Continued investment in Trafford’s greenspace resource is required in order to meet the objectives of Trafford’s Greenspace Strategy and hierarchy, as well as the strategic objectives of the Trafford Vision 2031 and Trafford’s Core Strategy as the spatial representation of The Trafford Partnership’s Community Strategy.
2.3The list of greenspace sites and associated provisional budget allocations have been developed in the context of available conditions surveys and inspection results in the form of:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.