Resolved
That the 2018/19 Internal Audit Plan be approved.
Accounts and Audit Committee approved this item on Tuesday 27 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That the 2018/19 Internal Audit Plan be approved.
The purpose of the report is to provide, at a high level, the proposed Internal Audit Operational Plan for 2018/19.
The Accounts and Audit Committee is asked to approve the 2018/19 Internal Audit Plan.
Contact person for access to background papers and further information:
Name: Mark Foster – Audit and Assurance Manager Extension: 1323
Background Papers: None Internal Audit Operational Plan 2018/19 – Audit and Assurance Service
1. Introduction
1.1The 2018/19 Internal Audit Operational Plan identifies the work to be undertaken by the Audit and Assurance Service during the year. This report describes its method of compilation and presents, at a high level, the 2018/19 Plan for approval.
2.1Each year the Audit and Assurance Service produces a report setting out its annual plan for approval by the Corporate Leadership Team (CLT) and the Accounts and Audit Committee. Subsequent updates are then provided to CLT and the Accounts and Audit Committee through the year highlighting work undertaken and progress against key areas of the plan. Actual work undertaken during the year against work planned is set out in the Annual Head of Internal Audit Report.
2.2In accordance with the Accounts and Audit Regulations 2015, it is a requirement that the Council “must undertake an effective internal audit to evaluate the effectiveness of its risk management, control and governance processes, taking into account public sector internal auditing standards or guidance.” The Audit and Assurance Service must undertake its work in accordance with the Public Sector Internal Audit Standards.
2.3The Service’s approach to undertaking internal audit work is set out in the Internal Audit Charter and Strategy documents. These were previously approved by CLT and the Accounts and Audit Committee in March 2017 and revised versions have been provided for approval in March 2018.
3. Compilation of the Internal Audit Plan
3.1The Operational Internal Audit Plan is produced to take into account coverage of risks and associated controls in place. At the end of the year an audit opinion is given as to the overall adequacy and effectiveness of the Council’s control environment, which encompasses internal control, risk management and governance. An important consideration is that the plan should include good coverage across Council services and systems.
3.2A number of factors are taken into account in compiling the plan based on both statutory obligations, the objectives of the Council and an assessment of risks. Factors such as materiality, business risks, inherent risks and time since the area was last reviewed are taken into account. Consideration is given to the Council’s six corporate priorities: - Low Council Tax and Value for Money - Economic Growth and Development
Internal Audit Plan 2018/19 2 - Safe Place to Live – Fighting Crime - Services Focussed on the most Vulnerable People - Excellence in Education - Reshaping Trafford Council.
There is audit coverage across each of the Council’s Corporate Directorates to reflect the various priorities and also authority-wide audit work to cover various strategic risks in relation to achievement of these objectives.
3.3New developments such as changes in legislation, organisational change and new policies and strategies are considered in planning work. For instance, coverage has taken into account the introduction of the General Data Protection Regulations from May 2018. Consideration will also be given to developments in relation to the Council’s Investment Strategy. Given the Council’s integration with Trafford CCG, Audit and Assurance will liaise with the CCG Internal Auditors to share plans and where relevant discuss findings and areas for future co-operation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
INTERNAL AUDIT OPERATIONAL PLAN 2018/19Report | 271 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.