RESOLVED - That the content of the report be noted, in particular: 1. The overview, principles and objectives of the proposed programme approach 2. The timeline and process to agreeing a new stability partner 3. The roles and responsibilities of each organisation 4. The key risks for the programme 5. The procurement process to be administered.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
The community services report is to update the Executive on the work undertaken to date and to note on the proposed programme approach going forward.
Recommendation(s)
That the Executive are to note the content of the report, in particular: 1. The overview, principles and objectives of the proposed programme approach 2. The timeline and process to agreeing a new stability partner 3. The roles and responsibilities of each organisation 4. The key risks for the programme 5. The procurement process to be administered.
Contact person for access to background papers and further information:
Name: Sara Radcliffe Extension: 0161 873 6081
Background Papers: None
Implications:
Relationship to Policy It will contribute to a number of the Council’s Framework/Corporate Priorities priorities including reducing Health inequalities and improving health and wellbeing.
Relationship to GM Policy or It will relate to the GM Transformation Portfolio Strategy Framework and GM Transformation themes 2 which is Transforming community based care & support.
Financial The programme approach will continue to address 1 cost pressures and aim to close the current funding gap.
There is a financial risk to CCG/TBC of full cost recovery from 1st April 2019 if programme approach is not delivered. Legal Implications: Procurement activities will be in accordance with the Public Contracts Regulations 2015 and associated legal advice will be provided to the Council and CCG throughout the process. Equality/Diversity Implications Not yet defined and if required will be developed as part of the task and finish groups Sustainability Implications Not applicable Resource Implications e.g. Staffing The programme will be resourced out of current / ICT / Assets resources. The ICT and Assets implications will be defined as part of the programme. Risk Management Implications 1. Operational Resilience – Deterioration in quality of service provision during the change 2. Contract Value – there is a funding gap on delivery arrangements. There is a risk of contract value not being agreed between PCFT and CCG. 3. Communications & Engagement – Proposals will not fully be supported by all stakeholders Health & Wellbeing Implications Sustainability of community services in Trafford Health and Safety Implications Not applicable
Background
1.1The contract between the CCG and Pennine Care Foundation Trust (“PCFT”) for delivery of community health services commenced 1st April 2013 for a period of 5 years to 31st March 2018. The contract included a provision to extend contract term for further 2 years.
1.2The parties have continued to operate under the terms and conditions of the contract since 31st March 2018.
1.3Following extensive work on the different options and after much discussion and consideration, on 3rd October 2018, the PCFT board ratified its decision to serve a notice to terminate the contract.
1.4The decision is based on what is best for the people of Trafford, and to ensure that community services remain resilient and sustainable. These services are facing increasing pressures, which has impacted on PFCT’s ability to deliver continuous improvement and innovation.
2 1.5 Discussions between the parties are on-going but, it is anticipated that the current contract will terminate on 31st March 2018.
2.0OVERVIEW, PRINCIPLES AND OBJECTIVES OF THE COMMUNITY SERVICE PROGRAMME APPROACH
2.1All partners remain absolutely committed to the development of high-quality community services and to working together to ensure these can play a significant and enhanced role in keeping people as independent as possible through integrated care close to home.
2.2The current model of integrated health and social care staff and services must now transfer to a new provider by or on 1st April 2019.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.