This report sets proposals for the Highway Capital Programme for the remainder of 2018/19 arising from scheme cost changes, efficiencies or reprogramming of existing 2018/19 funding whilst ensuring Capital funds are fully committed in order to maintain the standard of the asset portfolio.
The report reflects:
Changing condition of the asset Dealing with a range of stakeholder identified commitments Making suitable provision for works defined in the contract as requiring capital investment as opposed to revenue repairs or make safe
Recommendations
That the Executive:
1. Approve the updated highways programme as set out in the appendices to this report;
2. Delegates authority to the Corporate Director, Place to make subsequent minor changes to the agreed programme.
Contact person for access to background papers and further information:
Relationship to Policy This report relates to the corporate priority for Framework/Corporate Priorities economic growth and development.
Relationship to GM Policy or The programme aligns itself with the GM policy Strategy Framework and strategy framework and the Council maintains regular briefings of GM regarding its highways structural maintenance programme. Financial The proposed amendments to the Highways Structural Maintenance Programme will be contained within current budgets and the additional Local Transport Capital Grant Legal Implications The Council has a statutory duty to maintain highways which are maintainable at public expense. Equality/Diversity Implications No direct implications. Resource Implications e.g. Staffing No direct implications. / ICT / Assets Risk Management Implications The improvements proposed will reduce risk of claims and trips Health & Wellbeing Implications for all No highway direct users.. implications. Health and Safety Implications The improvements proposed will improve safety for all highway users.
Background
1.1At its meeting on the 21 February 2018, the Council approved the Council’s capital budget for 2018/19. That budget included £3.2m each year for highways maintenance from 2018/19 to 2020/21 and referred to a plan that was being prepared to address the current condition of the highway network.
1.2A review undertaken in line with the adopted Highways Infrastructure Asset Management Plan (HIAMP) established a need for additional funding targeted at reducing year on year deterioration over many years which would achieve an improvement in the overall road condition classification for Trafford, which is extremely important for inward investment, regeneration and keeping the network moving for businesses, residents and visitors in the Borough.
1.3Following the approval for an overall programme of £9.1m for the 2018/19 Highways Structural Maintenance Programme, a contingency was also earmarked at £0.874m, which was later reduced to £0.560m – when a further three additional schemes were allocated scheme specific funding. The contingency was included in case of cost overrun to ensure programme delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.