Resolved
RESOLVED – That the content of the report be noted.
Accounts and Audit Committee noted this item on Wednesday 30 October 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the content of the report be noted.
The purpose of the report is: To provide a summary of the work of Audit and Assurance during the period April to August 2019. To provide ongoing assurance to the Council on the adequacy of its control environment.
The Accounts and Audit Committee is asked to note the report.
Contact person for access to background papers and further information:
Name: Mark Foster – Audit and Assurance Manager Extension: 1323
Background Papers: None
1 This page is intentionally left blank
2 Audit and Assurance Service Report April to August 2019
Date: October 2019
3 1. Purpose of Report
This report summarises the work of the Audit and Assurance Service between April and August 2019 and highlights progress against the 2019/20 Internal Audit Plan to date. At the end of the year, these update reports will be brought together in the Annual Head of Internal Audit Report which will give the opinion on the overall effectiveness of the Council’s control environment during 2019/20.
2. Planned Assurance Work
Key elements of the 2019/20 Work Plan include: Fundamental Financial Systems reviews. Review work in relation to the 2018/19 Annual Governance Statement Continued input to and review of risk management arrangements and provision of guidance. Review of corporate procurement and value for money arrangements. Audit reviews in respect of ICT and information governance. Anti-fraud and corruption work, including the National Fraud Initiative. School audits and other establishment audit reviews. Grant claim certification work Audit reviews of other areas of business risk. Provision of guidance and advice to services across the Council.
3. Main areas of focus – April to August 2019
Work in this period included a particular focus on the following :
Audit review work in respect of financial systems including the issue of a number of audit opinion reports. Audit reviews undertaken as part of the ICT Audit Plan including follow up of previous review work. Completion of a significant part of the schools internal audit plan. Facilitating an update of the Strategic Risk Register for the Corporate Leadership Team. Input to the review of the Draft Annual Governance Statement prior to it being finalised. Continued progression of work supporting the National Fraud Initiative.
(All audit opinion reports completed or in progress are listed in Section 5 and other key areas of audit work undertaken are referred to in Section 6).
4. Summary of Assurances for April to August 2019
There were 17 internal audit opinion reports produced in the period, 9 final reports and 2 draft reports were issued. 6 other audit reports were produced with draft findings shared with management. A listing of audit report opinions issued including overall findings is shown in Section 5.
In respect of the final reports issued, opinions of "Medium” (Adequate) or above were given in relation to all reports. For all final reports issued, where applicable, agreed action plans are in place to implement the recommendations made.
4 5. Summary of Audit & Assurance Opinions Issued – April to August 2019 (See Appendix 3 for definitions of opinion levels, report levels and report status)
REPORT NAME -OPINION COMMENTS (DIRECTORATE) / -R/A/G (PORTFOLIO) by Coverage -Date Issued Level (1-4)
FINAL REPORTS ISSUED
Level 4 Reports :
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2019/20 AUDIT AND ASSURANCE REPORT FOR THE PERIOD TO AUGUST 2019Report | 438 KB | DownloadRead as text |
Follow Accounts and Audit Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Mar 2022 | MINUTESRESOLVED – That the Minutes of the Meeting held on 2 nd February 2022 be approved as a correct record and signed by t... | Approved | Open |
| 22 Mar 2022 | 2021/22 annual governance statement - approach / timetableRESOLVED - (1) That the timetable / action plan be noted. (2) That it be noted that the Committee would have input in... | Noted | Open |
| 22 Mar 2022 | Audit progress reportRESOLVED – That the content of the report be noted. | Noted | Open |
| 22 Mar 2022 | Budget monitoring report 2021/22 - period 10 (april 2021 - january 2022RESOLVED – That the updated positions on the revenue budget, collection fund and capital programme, and the observati... | Noted | Open |
| 22 Mar 2022 | Accounting concepts and policiesRESOLVED - (1) That the accounting concepts and policies that will be used in completing the 2021/22 annual accounts ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.