1) That the report be noted. 2) That Committee Members are asked to provide details on issues relating to C360 to the Corporate Director of Governance and Community Strategy. 3) That a detailed response be provided to the Committee on the performance ... view the full minutes text for item 14.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
To provide an update to the Scrutiny Committee on the progress made with the Council’s CRM system (C360) since the previous updates in January and October 2018.
Recommendation(s)
That the report is noted.
Contact person for access to background papers and further information:
Name: Sarah Curran Extension: 912 2823 Background Papers: None Background An earlier report to the Scrutiny Committee’s Task and Finish Group in January 2018 set out the background to the procurement of and functionality of the CRM system - C360
There were three recommendations made by the Scrutiny Committee in January 2018;
Recommendation 1 – That the Executive Member for Highways, Parks and Environmental Services continues to work closely with Amey on improving the interface between Amey systems and the Council’s CRM system to ensure residents and Members have an effective portal for reporting incidents, as well as ensuring that performance reporting is as accurate as possible.
Recommendation 2 – That the Executive consider conducting a review of the Council’s procurement process for large IT projects to ascertain whether any lessons can be learned following the procurement of the CRM system.
Recommendation 3 – That a further update on the CRM’s implementation be provided to Scrutiny in due course, reporting on progress against the timeline.
A further report to Scrutiny in October 2018 gave an update against the recommendations; Recommendation 1 – this had been completed Recommendation 2 - it was agreed that the Council would review the procurement process for any subsequent large IT project in the light of the lessons learned from the CRM project Recommendation 3 – the report of October 2018 gave the update which is below;
Service area Update Submit a compliment These went live in June 2018 and so far 2,000 Submit a comment compliments, comments and complaints have Submit a complaint been submitted
Green waste Form developed for taking payments for green waste permits. Waiting for decision on green waste payments before deploying Environmental Services ‘pay for it’ Forms developed for; Bulky Waste Collections, New and replacement bins Dropped Kerbs Final testing done, go live in October 2018 Environmental Services changes Forms developed. to live system (including extra Final testing done, go live in October 2018 closure reasons) Freedom of information and Form development completed, testing still to subject access requests do
Blue Car Badges Form development completed, testing still to do
Pest Control Form development completed, testing still to do
Registrars Forms development almost completed. Testing will then needs to be done
In October 2018 the Council was also in the process of agreeing a Change Control Notice (CCN) submitted by Civica to end the implementation programme and move to ‘business as usual’.
Current position
Work on the Change Control Notice had just started in October 2018 and it took longer than anticipated to complete due to a need to revisit some elements of the specification. Whilst this was ongoing Civica suspended work on the outstanding elements of the programme.
The table below provides the position as at March 2020
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Committee work programme 2025/261) That the work programme be noted. 2) That the work programme be updated by the Senior Democratic Support Officer a...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.