Resolved
- 1. That the content of the report be noted; 2. That, STAR will keep Joint Committee informed of any changes or implications from BREXIT.
STAR Joint Committee noted this item on Wednesday 16 December 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
- 1. That the content of the report be noted; 2. That, STAR will keep Joint Committee informed of any changes or implications from BREXIT.
The purpose of this report is to: Share the updated STAR Risk Register.
The recommendation of this report is that the Joint Committee Notes the contents of this report
Contact person for access to background papers and further information:
Name: Nichola Cooke Phone: [phone removed]
Financial Impact: Financial impact of income and savings included in risk register Legal Impact: Legal risks included in risk register Human Resources Impact: HR risks included in risk register
STAR Joint Committee – STAR Procurement Risk Register Asset Management Impact: None E-Government Impact: IT risks included in risk register Risk Management Impact: Risk monitoring and mitigation planning Health and Safety Impact: None
No public consultation required
Reasons for Recommendation(s)
The report is issued for information only.
1. Introduction
1.1The STAR Risk Register has been revised and updated in line with best practice. This is a live document that is reviewed regularly by STAR Wider Leadership Team (WLT) and reported to STAR Board and STAR Joint Committee annually, or by exception.
1.2Following Joint Committee, the STAR Risk Register is shared with all our Partners Audit teams for information and where appropriate inclusion in corporate risk registers.
2. Updates to Risk Register
2.1The STAR Risk Register has been reviewed by STAR WLT as part of the annual refresh and to reflect the position as a result of COVID-19.
2.2The risks can be summarised in the following heat maps:
2019 Heat Map (Total 20) 2020 Heat Map (Total 21)
Impact Impact 1 2 3 4 1 2 3 4 4 1 4 3 Probability Probability
3 1 3 2 2 6 2 8 1 4 5 3 1 3 2 3
2.3The new risks added are:
STAR Joint Committee – STAR Procurement Risk Register 021 - Reductions in income from Partners and Customers impacts on STAR budget and future sustainability 022 - New working from home arrangements impact of staff morale, and mental and physical health 023 - New legislation changes impact on Core Offer, compliance and workloads
2.4The risks removed are: 006 - Failure to deliver March 2020 restructure impacts on staff morale and service delivery 003 - Regional/GM strategies and growth of competition from external agencies impacts on STAR's ability to be sustainable
2.5The risks that have increased are: 015 - Failure to meet agreed in-year 5-STAR KPI targets 001 - Increases in running costs impacts on STAR budget and future sustainability 005 - Recruitment and retention of suitably qualified and/or experienced procurement staff impacts on ability to deliver services to Partners
2.6No risks have decreased in scoring.
3.1As a result of COVID we have seen an increase in the number of high graded risks and a slight increase in overall number of risks. Mitigation action are in place and will continue to be monitored and managed by STAR WLT.
4.1It is recommended that the Board: Notes the contents of this report.
Report Appendices
1. STAR Procurement Risk Register v3.0
STAR Joint Committee – STAR Procurement Risk Register Appendix 1: STAR Procurement Strategic Risk Register v3.0
Corporate Risk Register Version: 3.0
Issue Date: 19th November 2020
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
STAR PROCUREMENT STRATEGIC RISK REGISTERReport | 495 KB | DownloadRead as text |
Follow STAR Joint Committee at Trafford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Mar 2025 | Q3 performance and 2025/26 performance measures1) That the Committee agrees the STAR Key Performance Measures and Targets for 2025/26. 2) That the report be noted. | Agreed | Open |
| 21 Mar 2025 | Procurement act 2023 implementation update1) That the report be noted. | Noted | Open |
| 21 Mar 2025 | Q3 budget position - 3 year budget forecast and 2025/26 budget settingRESOLVED – That the Committee agrees the recommendations set out in the report. | Agreed | Open |
| 15 Jun 2022 | Membership of the committee 2022/23 including chairman and vice-chairmanThat at the start of the new Municipal Year the new chair nominated the vice chair and new membership be noted. | Noted | Open |
| 15 Jun 2022 | Quarter 4 5-star performance 2021/22(1) That the content of the report and performance to the end of Quarter 4 be noted. (2) That the Joint Committee con... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.