1) That the Content of the report be noted. 2) That the proposal to award the contract for the provision of parking enforcement and ancillary services to the winning bidder be approved. 3) That the delegation of authority to the Corporate Director for Place, in consultation with the Director of Legal and Governance and the Director of Finance and Systems, to agree final terms of the contract with the winning bidder be approved. 4) That the delegation of authority to the Director of Legal and Governance to enter into contracts as required to implement these recommendations be approved.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report details:- The reasons for procuring a contract for parking enforcement and ancillary services; The outline of the EU Tender process undertaken; The outcome of the selection process; The proposal to award a contract for the delivery of parking enforcement and ancillary services to the winning bidder.
Recommendation(s)
That the Executive: 1) Notes the content of the report; and 2) Approves the proposal to award the contract for the provision of parking enforcement and ancillary services to the winning bidder. 3) Delegate authority to the Corporate Director for Place, in consultation with the Director of Legal and Governance and the Director of Finance and Systems to agree final terms of the contract with the winning bidder; 4) Delegate authority to the Director of Legal and Governance to enter into contracts as required to implement these recommendations.
Contact person for access to background papers and further information:
Name: Sharon Walls, Head of Highways, Transportation and Greenspaces Extension: 4152
1 Implications:
Relationship to Policy Framework/Corporate Priorities Supporting people out of poverty and addressing our climate crisis. Financial The procurement exercise for this contract is within the current financial budget plans from April 2023.
Legal Implications: No direct implications Equality/Diversity Implications No direct implications Sustainability Implications No direct implications Carbon Reduction Implications The successful bidder has outlined a number of Social Value measures which includes the use of low emission vehicles within the contract lifetime. Staffing/E-Government/Asset This process does not require a Transfer of Management Implications Undertakings (Protection of Employment) Regulations 2006 (TUPE) as the successful contractor is currently the incumbent contractor for all three local authorities. Risk Management Implications Risks associated with this award are low as the successful contractor is incumbent in all three local authorities. Health & Wellbeing Implications No direct implications Health and Safety Implications No direct implications
1. Introduction
1.1Trafford’s current contract for Parking Enforcement services; Cash Collection/Pay and Display machine maintenance expires on 31st March 2023. In early 2022 Salford, Tameside and Trafford councils began the process of retendering for parking enforcement services, agreeing to do this by way of a joint procurement of three separate contracts, one for each council. It was agreed that Salford Council would lead the procurement exercise. It was anticipated that this joint exercise was likely to deliver services providing a financial outcome that demonstrated there were economies of scale for the same services across three councils. Whilst all operational costs are currently rising, including significant wage increases, Trafford’s overall contract price is achievable within the financial budget available for 2023/24 if the contract is awarded as recommended in this report. Trafford, Tameside and Salford councils have worked together to ensure that the new contract will deliver quality services and future proof services reviewing technology and smarter ways of deployment and ticketing in the future. This report sets out the details of the proposal to award a new ten year contract (incorporating an initial term of 5 years with an optional extension period of 2 years, plus a further 2 years and a final year) with a commencement date of 1st April 2023. . 2. Procurement Exercise
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.