Civic Quarter Heat Network - Approval to Accept Green Heat Network Fund Grant

Noted Executive 1 paper

Executive noted this item on Wednesday 18 December 2024. Below is the council's own wording, with the papers it was decided on.

Item68

Resolved

(1) That the contents of the report, be noted. (2) That the Executive approves accepting the grant if Trafford Council’s application is successful, and moving to the commercialisation phase of work, noting that a final decision to proceed will be taken once this phase has completed. (3) That the Corporate Director of Place, in consultation with the Director of Finance and the Director of Legal and Governance, be delegated authority to accept the Green Heat Network Fund grant if awarded at the level submitted. (4) That the Corporate Director of Place, following consultation with finance, legal and procurement, be delegated authority to carry out a procurement exercise to identify commercialisation advisers and a third-party delivery partner, and take all other necessary steps to develop the project prior to approval of a Joint Development Agreement. (5) That a further report be made to the Executive to seek approval of the Joint Development Agreement.
Word for word from the decision Trafford published for this meeting. Source: democratic.trafford.gov.uk

Follow this further

Built from Trafford's papers

What the report saysPro

Report to Executive

Summary

Trafford Council has applied to the Green Heat Network Fund (GHNF), for the proposed Trafford Civic Quarter Heat Network. This will provide up to £1m towards the commercialisation phase and £4.75m towards construction. At time of writing, the successful applications have not yet been announced. The purpose of this report is to seek Executive approval in principle to accept the grant and to proceed to the next stage of the project (commercialisation), and to also seek delegations to take forward the procurement of a third-party delivery partner.

Recommendation(s)

It is recommended that the Executive:

(i) Notes the contents of this report. (ii) Approves accepting the grant if Trafford Council’s application is successful, and moving to the commercialisation phase of work, noting that a final decision to proceed will be taken once this phase has completed. (iii) Delegates authority to the Corporate Director of Place, in consultation with the Director of Finance and the Director of Legal and Governance, to accept the GHNF grant if awarded at the level submitted. (iv) Delegates authority to the Corporate Director of Place, following consultation with finance, legal and procurement, to carry out a procurement exercise to identify commercialisation advisers and a third-party delivery partner, and take all other necessary steps to develop the project prior to approval of a Joint Development Agreement. (v) Notes that a further report will be made to the Executive to seek approval of the Joint Development Agreement

Contact person for access to background papers and further information: 1 Name: James Harries Extension: x

Background Papers: None

Appendices: None

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Civic Quarter Heat Network: Approval to Accept Green Heat Network Fund GrantReport 450 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
TR
Councillor Tom RossChair, present
CH
Councillor Catherine HynesDeputy Leader, present
SA
Councillor Stephen AdsheadCommittee Member, present
KC
Councillor Karina CarterCommittee Member, present
JH
Councillor Joanne HardingCommittee Member, present
LP
Councillor Liz PatelCommittee Member, present
JS
Councillor Jane SlaterCommittee Member, present
RT
Councillor Rose ThompsonCommittee Member, present
AW
Councillor Aidan WilliamsCommittee Member, present
JW
Councillor James WrightCommittee Member, apologies
JA
John AddisonDemocratic Services Officer, expected

On this subject at Trafford

Search all
  1. Civic Quarter Heat Network - Approval to Accept Green Heat Network Fund GrantThis decision
  2. Supplementary Item - Civic Quarter Area Action Plan: Formal AdoptionApproved
  3. Civic quarter action planApproved
  4. Civic quarter area action plan - approval and adoptionNoted
  5. Civic quarter area action plan - submission and examination stageApproved
  6. Civic Quarter Area Action Plan - Submission and Examination StageApproved

More from Trafford Executive

All decisions
MeetingDecisionOutcome
21 Sep 2026 Greater Manchester End to End Fostering Recruitment Hub1) That the national and Greater Manchester context supporting the developments of the Greater Manchester End-to-End ... Approved Open
21 Sep 2026 Sale Waterside Private Finance Initiative Exit1) That the hand back of the Sale Waterside PFI assets to Council ownership on expiry of the PFI contract on 28 th Oc... Approved Open
20 Jul 2026 Wharfside Strategic MasterplanThat the Executive: (i) Approves the draft Trafford for consultation. (ii) (ii) Delegates authority to the Corporate ... Approved Open
20 Jul 2026 Local Plan Regulation 19 Consultation ApprovalThat the Executive: (i) Approves the Trafford Local Plan (Publication Version) 2026, including allocations, designati... Approved Open
15 Jun 2026 Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies