1) That the Capital Programme as detailed in Section 2 and Appendix 1 be approved 2) That the schemes to be undertaken from the “block” budget allocations reported in paragraph 14 and detailed Appendix 2 be approved. That it be recommended that the Council approve: 3) The Capital Strategy including prudential and Local Indicators in section 1. 4) The overall Capital Programme in the sum of £308.62m for the period 2025/28 comprising £142.24m in respect of the General Capital Programme (as detailed in Section 2) and an Asset Investment Strategy gross expenditure budget of £166.38m for the period 2025/28 and continues to work within the previously approved budget envelope of £500m. 5) The flexible use of capital receipts as detailed in Capital Strategy (Section 2 paragraph 9). 6) Additional borrowing of £4.69m to be included within the three-year programme, as detailed in Section 2 paragraph 6.
Word for word from the decision Trafford published for this meeting.Source: democratic.trafford.gov.uk
This report highlights the Council’s investment plans for the next three years considering the estimated resources to be made available from Government as well as the Council’s own resources and consists of: - Capital Strategy including Prudential and Local Indicators (Section 1) – The Capital Strategy which includes the core principles that underpin the Council’s Capital Programme and details set indicators in accordance with the CIPFA Prudential Code which are designed to support decisions taken on affordability, sustainability and professional good practice. General Capital Programme (Section 2 and Appendix 1) - The level of resources forecasted to be available for general capital investment purposes during the period is £140.00m. The proposals included in this report will result in a general Capital Programme totalling £142.24m. This equates to £2.24m of over-programming over the three-year programme and will be reviewed each year to ensure actual capital resources are not overcommitted. To assist with the delivery of the capital programme individual scheme proposals are included for several key programmes. Details of Block Budget Allocations (Appendix 2) – Provides individual details of schemes that are covered by block allocations. Asset Investment Strategy (Section 3) – This report highlights the Council’s proposals to utilise the fund created during 2017 by acquiring a range of investment assets to facilitate development and regeneration whilst providing a sustainable revenue stream and covering any related borrowing costs and supporting local authority functions. Recommendations That Executive approves the: 1. Capital Programme as detailed in Section 2 and Appendix 1 2. Schemes to be undertaken from the “block” budget allocations reported in paragraph 14 and detailed Appendix 2. That Executive recommends the Council to approve: 3. The Capital Strategy including Prudential and Local Indicators in Section 1. 4. The overall Capital Programme in the sum of £308.62m for the period 2025/28 comprising £142.24m in respect of the General Capital Programme (as detailed in Section 2) and an Asset Investment Strategy gross expenditure budget of £166.38m for the period 2025/28 and continues to work within the previously approved budget envelope of £500m. 5. The flexible use of capital receipts as detailed in Capital Strategy (Section 2 paragraph 9) 6. Approve additional borrowing of £4.69m to be included within the three-year programme, as detailed in Section 2 paragraph 6.
Contact person for access to background papers and further information: Name: Frank Fallon Extension: 4170 Background Papers – None
Background
1. The Capital Strategy focuses on the core principles that underpin the Council’s capital programme and gives a position statement with regards to capital expenditure and the resources available. It also reviews the key issues and risks that will impact on the delivery of the Council’s capital investment plans and the governance framework required to support delivery of the Strategy.
2. The three-year capital programme that was approved in February 2024 was £154.56m. Progress against this programme has been reported to Executive throughout the financial year as part of the budget monitoring report. 3. The three-year Capital Programme 2025/28 and update of available resources is detailed in Section 2. This gives a proposed General Capital Programme of £142.24m for the next three years and an Asset Investment Programme of £166.38m to give a total capital programme of £308.62m.
Implications:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Trafford Good Growth Plan 2026/27(1) That the progress achieved against the actions contained in the Inclusive Economy and Delivery Plan, be noted. (2...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.